ASHRAE OR-16-C075-2016 CFD Design and Validation of a Thermal Storage Tank System and Its Impact in a Design-Build Project.pdf
《ASHRAE OR-16-C075-2016 CFD Design and Validation of a Thermal Storage Tank System and Its Impact in a Design-Build Project.pdf》由会员分享,可在线阅读,更多相关《ASHRAE OR-16-C075-2016 CFD Design and Validation of a Thermal Storage Tank System and Its Impact in a Design-Build Project.pdf(8页珍藏版)》请在麦多课文档分享上搜索。
1、 Reza Ghias is the Director of Advanced Simulation Center (ASC) and Mike Kilkeary is an Associate Principal Engineer, both from Southland Industries located in Dulles, Virginia CFD Design and Validation of a Thermal Storage Tank System and Its Impact in a Design-Build Project Reza Ghias, DSc Michael
2、 Kilkeary, PE ASHRAE Member ASHRAE Member ABSTRACT The use of advanced engineering tools in HVAC industry has increased as the cost of computational fluid dynamics (CFD) has become more affordable for engineering firms. A thermal storage tank system utilized a series of vertical tanks to store chill
3、ed water and supplement chillers in the event of a power failure. Chilled water is routed from the storage tanks to critical equipment during chiller re-start, bridging the gap in time that the chillers are unable to provide set-point chilled water due to power failure and subsequent required time t
4、o re-start. The main challenge of the tank sizing was to optimize the tanks in order to maximize the output time of stored chilled water while minimizing the height and quantity of the tanks. The goal was achieved through an innovative design in which the tank diffusers were designed through a serie
5、s of simulations. Once installed, the system was tested rigorously to the same conditions that were previously simulated during design. The result of field-testing verified that the CFD model was accurate within two percent margin of error. Utilization of this process allowed the design-build team t
6、o save installation time, money, materials, and building square footage by reducing the number of required storage tanks to provide the required stored chilled water quantity. INTRODUCTION One of the many benefits of the Design-Build project delivery method is that the owner can define their needs a
7、nd allow the design-build contracting team the flexibility and the freedom to develop innovative solutions to meet their needs, not be constrained by rigid prescriptive design requirements, all wrapped into a competitive bid environment. Contractors enjoy the challenge of using design creativity to
8、meet the owners needs, reduce the cost of the project, and deliver the project faster than traditional design-bid-build delivery. The price of that freedom for contractors is the design risk. The Request for Proposal (RFP) response phase of a design-build project is generally a relatively short peri
9、od of time in which the contracting teams have to identify the key design challenges of the project, develop engineering solutions, and balance price and schedule ramifications of those solutions with the overall project constraints. The competitive bid environment encourages design teams to utilize
10、 innovative thinking, while the short RFP response period limits the amount of technical development the design engineering team can incorporate into the overall solution (Zhai 2006). This juxtaposition of requirements for the design team promotes them to utilize non-traditional methods for verifica
11、tion and validation of their design. CFD analysis, once considered too time consuming and expensive for conventional architectural/engineering building design, is now a design tool that is frequently used to predict results and remove ambiguities of the design process. Developing reliable CFD models
12、 for industrial applications and utilizing high performance computing (HPC) machines provide quick turnaround alternatives for the design team. The team can use these results to make design decisions, influence alternatives with respect to cost and scheduling, and create presentation graphics and vi
13、deos that convey the design solution to the owner with more than a “just take our word for it” response. For the project referenced in this technical paper, the task was to design and build a chilled water thermal storage system that would provide fifteen (15) minutes of chilled water in the event o
14、f a power loss and subsequent loss of active chillers. Fifteen minutes was required in this data center application in order to bridge the gap in time that the chillers are unable to provide set-point chilled water due to power failure and subsequent required time for those chillers to re-start and
15、energize to full capacity. An optimal design would maximize the output time of stored chilled water while minimizing the height and quantity of the tanks required. The solution would need to be robust enough to maintain a tight tolerance on chilled water supply temperature and distribution time, but
16、 simple enough to maintain competitive cost control. Many parameters can affect the performance of the storage tanks, and extensive experimental and numerical studies have analyzed these parameters (Karim 2009, Ghadar 1989, Bahnfleth 2003, Yoo 1986, Zurigat 1991, Stewart 1992). Figure 1(a) shows a t
17、hermal storage tank with charge and recharge diffusers at the top and bottom of the tank to distribute and recollect the water in the tank uniformly. The uniform flow distribution is more crucial in shorter tanks in which flow turbulences can deteriorate the thermocline that are formed due to buoyan
18、cy effect. Hudson et al. (1979) found that a ratio of half between the total opening area in the diffuser branches to the cross sectional area of the corresponding branch pipe can help the flow uniformity. In other words, the total slot area at each branch should be half of the heara of the pipe tha
19、t slots are created on. Figure 1 (a) Schematic of the thermal tanks to provide cool water at 60 F for at least 15 minutes. (b) Schematic of the double-ring diffuser with different slot sizes, which are highlighted on each branch of the inner and outer loops. The low velocity at inlet slots is anothe
20、r key factor to keep buoyancy force dominant enough to form the thermocline effectively. Dorgan and Elleson (Dorgan 1994) investigated the swirling in the tank as a result of non-uniform velocity at diffuser slots and suggested that uniform static pressure in diffuser pipes can provide uniform disch
21、arge velocity at slots. The comprehensive reviews and studies on radial and octagonal diffusers were performed by Dorgan and Elleson (Dorgan 1994) and Bahnfleth et al.(2003) and readers are referred to mentioned references for additional details. CFD MODELING The main challenge of the tank sizing wa
22、s to optimize the thermocline in the tanks in order to maximize the output time of stored chilled water while minimizing the height and quantity of the tanks. This was achieved through an innovative procedure in which the tank diffusers were designed through a series of simulations. Reynolds-average
23、d Navier-Stokes equations along with realizable k- two-equation turbulence available in a commercial iterative and control volume base solver were used for all numerical simulation performed in this paper. Figure 2 presents the domain and boundary conditions used for the simulations. Figure 2 Bounda
24、ry conditions set up for thermal storage system. The return flow from the data center enters the first tank at 76 F (24.4 C) with flow rate of 1540 GPM (97.16 L/s). The system provides chilled water at 60 F (15.6 C) at its outlet of last tank. The water inlet temperature was at 76 F (24.4 C) with ve
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAEOR16C0752016CFDDESIGNANDVALIDATIONOFATHERMALSTORAGETANKSYSTEMANDITSIMPACTINADESIGNBUILDPROJECTPDF

链接地址:http://www.mydoc123.com/p-455798.html