ASHRAE NA-04-7-1-2004 Using Certification Data of Cleanrooms to Determine Degradation and Retrofit《使用认证数据的洁净室 以确定退化及改造》.pdf
《ASHRAE NA-04-7-1-2004 Using Certification Data of Cleanrooms to Determine Degradation and Retrofit《使用认证数据的洁净室 以确定退化及改造》.pdf》由会员分享,可在线阅读,更多相关《ASHRAE NA-04-7-1-2004 Using Certification Data of Cleanrooms to Determine Degradation and Retrofit《使用认证数据的洁净室 以确定退化及改造》.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、NA-04-7- 1 Using Certification Data of Cleanrooms to Determine Degradation and Retrofit Susan D. Morrison Member ASHRAE ABSTRACT What should be looked at in determining the retrofit of a cleanroom? This veT expense environment andpiece of infa- structure has a history or sewice life cost to its exis
2、tence. This history and case study of a cleanroom will show some of the overlookedparameters that should be used in this type of eval- uation, which are often overlooked by engineers. When we, as engineers, design a cleanroom and do the initial commissioning, it is probable that we will never see th
3、is cleanroom again. But if we are lucky enough to go back to a cleanroom that is having problems, we can try to find the “fly in the ointment,” so to speak, as I was able to do in the summer of 1999. One of the first questions we tend to ask ourselves is, “Where do 1 begin? It is important to rememb
4、er that many of us design, build, and certify cleanrooms. Yet we know little of the testing and validations as well as modifications that have taken place since our original involvement. Keeping this in mind, if we went right back to the original test documents and then requested all subsequent cert
5、ification tests conducted since that time, we might see when problems started to develop. Having done the initial, design, construction, and commissioning of this cleanroom complex, and having set the baseline, provided me insight as to what had happened, whether an overhaul was needed, and how to c
6、orrect it if needed. The first things needed were the original performance matrix and original test report for this facility. It was critical to know the performance baseline of the facility at commission- ing, including the original heat loads and particle generation levels in the at-rest mode. Thi
7、s was also a unique cleanroom, as it had been designed with a night setback. All of the tests had to be performed in the unoccupied mode to prove the environ- ment could sustain the metrology when we decreased the airflow to 50%. The cleanroom requirements utilized certifi- cation parameters, which
8、included more than just particle counts. These items should not be confused with control commissioning or HVAC commissioning and are parameters that are decided upon by the customer and designer for the interior of the cleanroom. These cleanroom requirements included lighting levels, which were to a
9、verage 100 or 70 foot candles, on average, depending on area; sound, which was not to exceed 80 decibels; airflow that was temperature of 22C; and humidity ofnot less than 30%. Pressure was decided to be a minimum of 10 to a maximum of 30 Pa between zones, and the air change rate was between 20 to 8
10、0 ach, based on the class of the room. Lets look at the data from some of the rooms from the initial commissioning throughout the development of operational problems. When we look at these data, it is useful to remember that these cleanrooms are unlike a standard cleanroom in that the heat load was
11、balanced against the makeup air for pressuriza- tion and the process exhaust; these factors determined the capacity of the coil. In these rooms, heat load was very tightly balanced and the units could be kept within their size limita- tion requirements. Heat load-both latent and sensible- generated
12、in the room was handled by the return retreating the air as well as process exhaust. Makeup air had to be treated to replace air consumed for process exhaust and pressurization; this volume of makeup air that flows through the coil only once needs to be conditioned in this one pass to the required t
13、emperature and humidity for the cleanroom. The volume of air needed to flow through HEPA filters in order to maintain the classification of the cleanrooms determined the recircu- lated air volume (see Figure 1). When we factor this all in to one room, we have a very tightly balanced metrology. That
14、results in a relationship in which very small changes to process loads will have a large effect on the overall performance of the cleanroom, not only in heat load, but also potentially in parti- cle generation and the retention of these particles in the airstream. Susan Morrison is facilities safety
15、 manager at Paratek Microwave, Columbia, Md. 02004 ASHRAE. 755 Table 1. Excerpt from Occupied Room Matrix I I Make Up AJr -D!schaqe- -Return Arc-. I t Figure I Air-handling schematic. Understanding this basic design concept and the matrix of the design (see Table i), we can then begin to look at wha
16、t has occurred to the cleanroom when we graph these parameters. One of the first parameters we will begin with is the airflow while the room is occupied (see Figure 2). The first thing that has to be established under IES-RP-CC-006-84-T Sections 3 and 4, which deal with air flow uniformity, is to me
17、et *20% uniformiy of the design airflow. This percentage of uniformity between individual filters in a room must be achieved as agreed upon by the buyer and seller. As shown in Figure 2, at the time of initial certification, we fell well within these parameters. The difference between total airflow
18、that was tested in 1995 and design was *20% or less of design. We should look at the deviation not only as shown in Figure 2 but also filter- to-filter. If we take a look at the data in Figure 2, the first thing we notice is the strange failure of the airflow total of Rooms 9 and 10 in 1998. If we w
19、ere to look at the uniformity from HEPA filter to HEPA filter, we would find uniformity between these filters at less than *8%. But why reference and use an out-of-date IEST standard? It was out of date at the time this project took place, but it was what the customer wanted and demanded! When we lo
20、ok at a project, it always helps to look at what was required in the contract at the time it was constructed, not what it is today. Sometimes, in an evaluation of an existing space, we neglect to find out how the space was intended to work and apply standards based on todays knowl- Air Flow 6000 500
21、0 gDesign ml995 01997 Y 1998 z 4000 2 3000 D g 2000 Il999 1000 O 14 131211 10 9 2 8 7 5 4 6 Room # Figure 2 Occupied airflow. edge without regard for the original design intent. It is impor- tant to remember that there are many recommended standards and practices out there, and some customers want w
22、hat they want even if you tell them it is out of date-a good example of this was IES-RP-CC-006-84-T, which was used on this job site. They wanted all air in cubic meters an hour and particles in concentration per cubic foot of air. This can get very confus- ing, but this type of mix exists out there
23、, and it is necessary for us to maintain a library of these items for reference when reviewing certification data for analysis. Lets look at the particle counts (see Figure 3) for the actual locations from the same time periods to see if there is a correlation. We find that the particle counts were
24、higher in those rooms by as much as 250% in 1998 compared to the 1997 and 1999 tests. These particle counts were below the limit estab- lished by Federal Standard 209E of 10,000 particles at 0.5 um per cubic foot of air. It was curious to see what could have happened between 1997 and 1999. When we l
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAENA04712004USINGCERTIFICATIONDATAOFCLEANROOMSTODETERMINEDEGRADATIONANDRETROFIT 使用 认证 数据 洁净室 确定 退化

链接地址:http://www.mydoc123.com/p-455512.html