ASHRAE LV-11-C015-2011 Myths and Realities of Indirect Evaporative Cooling Thermodynamic Performance.pdf
《ASHRAE LV-11-C015-2011 Myths and Realities of Indirect Evaporative Cooling Thermodynamic Performance.pdf》由会员分享,可在线阅读,更多相关《ASHRAE LV-11-C015-2011 Myths and Realities of Indirect Evaporative Cooling Thermodynamic Performance.pdf(12页珍藏版)》请在麦多课文档分享上搜索。
1、 Dr. Des Champs is a consultant to Munters Corporation of Buena Vista, Virginia Myths and Realities of Indirect Evaporative Cooling Thermodynamic Performance Nicholas H. Des Champs, Ph.D., P.E. Fellow ASHRAE ABSTRACT With the aid of a newly developed finite-difference computer program, that predicts
2、 the performance of heat exchangers when used as Indirect Evaporative Coolers (IEC), various flow and heat exchanger arrangements are analyzed for overall system cooling performance. One example investigates the use of cooled, dry air resulting from the first pass of an IEC for use as scavenger air
3、in a follow-on IEC heat exchanger for the purpose of increasing the overall system wet-bulb depression efficiency. A second example investigates using an IEC to generate cooled water, as opposed to cooled air, for supplemental cooling in a chilled water system. A third involves predicting the maximu
4、m performance expected by drawing off cooled, dry air as it progresses through an IEC and using this air to feed into the wetted scavenger air flow so as to eventually consume approximately half of the original inlet, dry air as lowered wet-bulb temperature air to be scavenger air for the evaporativ
5、ely cooled flow channels of the IEC heat exchanger. Other concepts are presented, such as using a direct evaporative cooler to pre-cool air for a condenser coil while simultaneously cooling the sump-water temperature of an IEC to enhance its effectiveness. INTRODUCTION With the tendency toward zero
6、energy design for buildings, there has been a greater interest in the energy-savings aspects of utilizing the cooling effects of evaporating water to reduce energy usage in air-conditioning systems. By far, when using the cooling effects of water, evaporative cooling of outdoor air is produced by ha
7、ving the air come in direct contact with a wetted media where energy from the air is used to evaporate water in an adiabatic process. This process results in a lowered dry bulb temperature. It is a very simple process, but Direct Evaporative Cooling (DEC) may introduce too much moisture to the space
8、 which has led to the use of Indirect Evaporative Cooling (IEC), or a combination of IEC and DEC when space relative humidity is a concern. Implementing the IEC process requires the use of an air-to-air heat exchanger. Any of the commonly used air-to-air heat exchangers, such as plate, heat pipe, or
9、 tube meet the requirements. IEC using air-to-air heat exchangers began to show up in the market place in the mid 70s, initially to utilize the exhaust wet-bulb, as opposed to the exhaust dry bulb temperature, to increase recovery efficiency. During the 80s, the IEC concept moved principally to arid
10、 regions and applied to cooling outdoor air with outdoor air (or possibly returns air) and the resulting cooled, dry air stream delivered to the space. In addition, the use of various combinations of IEC, DEC, and cooling coil to condition the supply air in the most efficient manner for a specific a
11、pplication became the norm. There are two basic methods to cool the supply air within the air-to-air heat exchanger during an IEC process. The first is to use a DEC to lower the “working air stream,“ or scavenger air, temperature to within a few degrees of initial scavenger wet-bulb temperature and
12、then direct this cooled, moist air through one side of the heat exchanger that cools the supply air in adjacent flow channels (this process also allows use of energy recovery wheels). Figure 1 is a schematic of a unit that uses DEC media to cool air prior to it traversing the scavenger side of an IE
13、C air-to-air heat exchanger, showing the temperature entering and leaving the components. The second method is to have the entire thermodynamic process take place within the IEC heat exchanger, thus eliminating the DEC. In this case, water continually sprays on the scavenger-channel surface where ev
14、aporation takes place because of the scavenger air flowing over the wetted surface. The cooled water cascades over the scavenger-side surface and absorbs heat, through the tube wall, from the hot, dry air stream. The water flows by gravity to the sump, under the heat exchanger, from which a pump del
15、ivers it to the spray nozzles above the heat exchanger to complete the water recirculation process. Figure 2 is a schematic of the integral IEC heat exchanger that uses its scavenger-side surface as the evaporative cooler or “cooling tower“ with thermal performance shown for this type of IEC product
16、. LV-11-C015 2011 ASHRAE 1192011. American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Transactions, Volume 117, Part 1. For personal use only. Additional reproduction, distribution, or transmission in either print or digital form is n
17、ot permitted without ASHRAES prior written permission.An IEC system must withstand the difficult environment of sprayed water, with its scaling and corrosion properties as well as extreme sunlight and temperature. It should also be price competitive and present no greater maintenance cost when compa
18、red to conventional air-conditioning equipment. Figure 1 Drawing of an IEC unit showing typical airflow and temperatures using DEC media to cool air prior to passing through the scavenger side of a plate-type air-to-air heat exchanger. Figure 2 Integral cooling tower and air-to-air heat exchanger. 1
19、20 ASHRAE TransactionsNormally, the initial installed cost of an IEC system is greater than a DX system so the overall energy performance of the IEC must be significant in order for the engineers and owners to become interested in their use. An estimate of the total market for IEC systems using air-
20、to-air heat exchangers, in North America, is less than $50,000,000 per year, a small percentage of its potential sales. There are several reasons, 35 years after its introduction, for lack of consideration of the concept, with the principal two reasons being high initial cost and above average maint
21、enance. Inadequate thermal performance is another important reason. An ongoing problem with IEC heat exchangers is lack of necessary analytical tools to aid in the thermodynamic design process. Predicted IEC performance usually is the result of tests performed on a prototype that is relatively easy
22、to build. The testing procedure should, but seldom does, follow the guidelines set forth in ANSI/ASHRAE 143-2007, Method of Test for Rating Indirect Evaporative Coolers. Extrapolating data from an unreliable testing program leads to unpredictable field results. A principal reason that there is a lac
23、k of analytical tools for use by manufacturers is the relative complexity of the interaction of various physical and thermodynamic effects taking place within an IEC heat exchanger. Using a finite-difference program, developed by the author, that considers essentially all of the twenty-five or more
24、inputs that are necessary to define the IEC system and process, several examples illustrate that the predicted performance is sometimes not what might be anticipated. A LIMITED COMPARISON BETWEEN COOLING TOWERS AND IEC EQUIPMENT Figure 3a is a schematic diagram of an indirect-contact evaporative coo
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAELV11C0152011MYTHSANDREALITIESOFINDIRECTEVAPORATIVECOOLINGTHERMODYNAMICPERFORMANCEPDF

链接地址:http://www.mydoc123.com/p-455418.html