ASHRAE AN-04-11-2-2004 Smoke Control and the International Building Code《烟气控制和国际建筑守则》.pdf
《ASHRAE AN-04-11-2-2004 Smoke Control and the International Building Code《烟气控制和国际建筑守则》.pdf》由会员分享,可在线阅读,更多相关《ASHRAE AN-04-11-2-2004 Smoke Control and the International Building Code《烟气控制和国际建筑守则》.pdf(8页珍藏版)》请在麦多课文档分享上搜索。
1、AN-04-1 1-2 Smoke Control and the International Building Code John H. Klote, D.Sc., P.E. Fellow ASHRAE ABSTRACT This paper is an overview of the smoke controlprovisions of Section 909 of the 2000 Intemational Building Code (IBC). The IBC allows third-party testing/commissioning and third- party assi
2、stance in review of design aspects. A rational anal- ysis in accordance with well-established engineering princi- ples is specifically required. This analysis must include “suflcient information anddetail” to demonstrate compliance with the code. The code has requirements for the tightness of smoke
3、barriers. Smoke control can be achieved by the pres- surization method, the airflow method, or the exhaust method. The IBC has specijc requirements for the minimum size of a design jire. INTRODUCTION The International Building Code (IBC) was developed by the International Code Council to replace the
4、 three model building codes (BOCA 1999; ICBO 1997; SBCCI 1997). This paper is an overview of the smoke control provisions of Section 909 of the 2000 IBC (ICC 2000), but not all require- ments and exceptions are addressed. For the specific code requirements, readers should see the IBC. For a more det
5、ailed discussion of smoke control with reference to the IBC, see Evans and Klote (2002). For exhaustive information including the fundamental mathematics about the entire topic of smoke management, see Klote and Milke (2002). A coordinated effort among all involved parties is needed to meet the smok
6、e protection provisions of the code. It cannot be overemphasized that the design professionals, including the architect, mechanical engineer, electrical engineer, fire protection engineer, building oficial, and fire chief, as well as all applicable trades, including the fire alarmelectrical Douglas
7、H. Evans, P.E. contractor(s), automatic sprinkler contractor, mechanical contractor, and those responsible for construction of smoke barriers, must work together to accomplish a fully functional smoke control system. Permit applications for architectural, mechanical, and electrical submittals should
8、 not be approved until all aspects of the smoke control system are adequately coordinated. Until applicable fire protection aspects are coor- dinated, renovations and demolition permit applications for existing buildings may also need to be held. It is important to think of fire protection in terms
9、of systems. These systems include the passive barriers (walls and floors) along with the active systems (automatic sprinklers, fire detectiodalarm systems, air-handling equipment, etc.). These systems must work together to achieve a consolidated coordinated approach to fire protection. Section 909 o
10、f the IBC describes both mechanical and passive smoke control systems. Compliance with this section is only required when so directed by other provisions of the code. The purpose of Section 909 is to establish minimum requirements for the design, installation, and acceptance test- ing of smoke contr
11、ol systems that are intended to provide a tenable environment for the evacuation or relocation of occu- pants. Mechanical systems are not mandated. Passive contain- ment may also be used as a viable option to provide a tenable environment for the evacuation or relocation of occupants. The provisions
12、 of Section 909 are not intended for the preser- vation of contents, the timely restoration of operations, or for assistance in fire suppression or overhaul activities. This paper discusses (1) special inspection and test requirements, (2) rational analysis, (3) smoke barrier construction, (4) smoke
13、 control by the pressurization method, John H. Mote is a consulting engineer at Fire and Smoke Consulting, Leesburg, Va. Douglas H. Evans is a fire protection engineer with Clark County Building Department, Las Vegas, Nev. 638 I 02004 ASHRAE. (5) smoke control by the airflow method, (6) smoke contro
14、l by the exhaust method, and (7) determination of a design fire. SPECIAL INSPECTION AND TEST REQUIREMENTS Section 909 was written to allow not only third-party test- ing/commissioning but also assistance in review of design aspects. If the building official feels that departmental staff does not hav
15、e either the time or expertise to adequately review smoke control systems in accordance with Section 909, third- party review may be utilized. Compliance with Section 909 is recognized as one option in meeting the requirements of Section 410.3.7.2 for stage ventilation. Similarly, Section 1008.5.2.1
16、 allows compliance with Section 909 as one option for smoke-protected assembly seating. The other option this section allows is “natural venti- lation.” When the facility is substantially open to the atmo- sphere, natural ventilation can provide protection within the intent of the code. If the facil
17、ity is enclosed, a smoke reservoir calculated in accordance with the exhaust method of Section 909 is necessary to ensure compliance. RATIONAL ANALYSIS A rational analysis in accordance with well-established engineering principles is specifically required. This means that the design must be based on
18、 mathematical calculations using known laws ofphysics. The engineer ofrecord is respon- sible for designing a system that will function properly to fulfill the requirements of Section 909. The desiver is required to include “sufficient information and detail” to demonstrate compliance, as well as gi
19、ve the respective contractors sufficient information to construct the system. When requested by the authority having jurisdiction (AHJ), substantiation of a thorough analysis of the conditions outlined in Section 909.2 must be submitted for review and approval. The analysis needs to address stack ef
20、fect, temperature effect of the fire, wind effect, HVAC systems, climate, and duration of operation. The system must be designed such that the maximum probable normal or reverse stack effect will not adversely interfere with the systems capabilities. In determin- ing the maximum probable stack effec
21、t, altitude, elevation, weather history, and interior temperatures need to be used. Section 909.9 states that buoyancy and expansion caused by the design fire must be analyzed. The system needs be designed such that these effects do not adversely interfere with the systems capabilities. The design n
22、eeds to consider the adverse effects of wind. Wind effect can impact the placement, orientation, and type of fans used. Wind speed is dependent on the height above grade and the surrounding terrain. Therefore, the level of the space, the side of the building, adjacent obstructions (such as build- in
23、gs), and type of equipment need to be considered. The design needs to consider the effects of the heating, ventilating, and air-conditioning (HVAC) systems on both smoke and fire transport. The analysis must include all permutations of systems status. The design must consider the effects of the fire
24、 on the HVAC systems. With respect to climate, the design needs to consider the effects of low temperatures on systems, property, and occu- pants. Air inlets and exhausts must be located so as to prevent snow or ice blockage. All portions ofthe smoke control system must be protected from adverse wea
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAEAN041122004SMOKECONTROLANDTHEINTERNATIONALBUILDINGCODE 烟气 控制 国际 建筑 守则 PDF

链接地址:http://www.mydoc123.com/p-454531.html