ARMY UFGS-33 52 43 13-2010 AVIATION FUEL PIPING《航空燃油管路》.pdf
《ARMY UFGS-33 52 43 13-2010 AVIATION FUEL PIPING《航空燃油管路》.pdf》由会员分享,可在线阅读,更多相关《ARMY UFGS-33 52 43 13-2010 AVIATION FUEL PIPING《航空燃油管路》.pdf(40页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-33 52 43.13 (February 2010)-Preparing Activity: USACEUNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION TABLE OF CONTENTSDIVISION 33 - UTILITIESSECTION 33 52 43.13AVIATION FUEL PIPING02/10PART 1 GENERAL1.1 REFERE
2、NCES1.2 ADMINISTRATIVE REQUIREMENTS1.3 SUBMITTALS1.4 QUALITY ASSURANCE1.4.1 Welding Qualifications1.4.2 Qualifications of Welders1.4.2.1 Weld Identification1.4.2.2 Defective WorkPART 2 PRODUCTS2.1 MATERIALS AND EQUIPMENT2.1.1 Carbon Steel Piping2.1.1.1 Interior Epoxy Coated Carbon Steel Piping2.1.1.
3、2 Coat Testing2.1.2 Stainless Steel Piping2.1.3 Protective Coatings for Aboveground Piping2.1.3.1 Coating Description2.1.3.2 Mixing Epoxy-Polyamide Coatings2.1.3.3 Induction Times2.1.3.4 Epoxy-Polyamide Coating Application2.1.3.5 Equipment Cleanup2.1.4 Protective Coatings for Buried Steel Piping2.1.
4、5 Fittings2.1.5.1 General2.1.5.2 Carbon Steel Fittings2.1.5.3 Stainless Steel Fittings2.1.5.4 Isolating Gasket Kits (Insulating) for Flanges2.1.6 Bolts and Nuts2.1.7 Gaskets2.1.8 Relief and Drain System Piping2.1.9 Relief and Drain System Protective Coating2.1.10 Field Applied Protective Coatings2.1
5、.10.1 Welded Joints2.1.10.2 Tape for FittingsSECTION 33 52 43.13 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-2.1.11 Threaded Joints2.1.12 Welded Joints2.2 MANUAL VALVES2.2.1 Ball Valves2.2.1.1 Materials2.2.1.2 Full Port Ball (DBBV) Valves f
6、or Piggable Lines2.2.1.3 Electric Valve Actuator2.2.2 Plug (Double Block and Bleed) Valves2.2.2.1 General2.2.2.2 Valve Operation2.2.2.3 Relief Valves2.2.2.4 Bleed Valves2.2.2.5 Electric Valve Actuator2.2.3 Swing Check Valves2.2.4 Silent Check Valves2.3 RELIEF VALVES2.3.1 Valve Materials2.3.2 Sight F
7、low Indicators2.4 PIPING ACCESSORIES2.4.1 Flexible Ball Joints2.4.2 Pipe Sleeves2.4.3 Strainers2.4.3.1 Basket Type2.4.3.2 Cone Type (Temporary)2.4.4 Pipe Hangers and Supports2.4.4.1 General2.4.4.2 Adjustable Pipe Supports2.4.4.3 Low Friction Supports2.4.4.4 Concrete and Grout2.4.5 Sample Connections
8、2.4.6 Flanged Swivel Joints2.4.7 Monitoring Points2.4.8 Fuel Hose2.4.9 Pressure Fueling Nozzle2.4.10 Nozzle Adapter (SPR)2.4.11 Pigging Accessories2.4.11.1 Closure Door2.4.11.2 Signaler2.5 FLEXIBLE HOSES2.6 AUTOMATIC AIR VENT2.7 SURGE SUPPRESSOR TANK AND VALVEPART 3 EXECUTION3.1 VERIFICATION OF DIME
9、NSIONS3.2 CLEANING OF PIPING3.3 TRENCHING AND BACKFILLING3.4 PIPING LAYOUT REQUIREMENTS3.4.1 Pipe Fabrication3.4.2 Interferences and Measurements3.4.3 Space and Access3.4.4 Location3.4.5 Piping and Equipment3.4.6 Structural Support3.4.7 Grade3.4.8 Size Changes3.4.9 Direction Changes3.5 WELDING3.5.1
10、GeneralSECTION 33 52 43.13 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3.5.2 Tests3.5.3 Standards of Acceptance3.5.4 Corrections and Repairs3.5.4.1 Defect Removal3.5.4.2 Methods of Defect Removal3.5.4.3 Rewelding3.5.4.4 Peening or Caulking3
11、.6 INSTALLATION3.6.1 Precautions3.6.2 Protective Coatings3.6.2.1 Application of Tape Wrapping3.6.2.2 Inspection and Testing3.6.2.3 Damage Repair3.7 INTERIOR EPOXY COATING3.8 INSTALLATION OF UNDERGROUND PIPE3.8.1 Pipe Assembly3.8.2 Warning Tapes in Earth Trenches3.8.3 Clearances3.8.4 Protective Coati
12、ng3.9 TESTING3.9.1 Pneumatic Test3.9.1.1 Pneumatic Test Procedure3.9.1.2 Hydrostatic Test3.9.2 Performance Testing3.10 PIPELINE PIGGING VERIFICATION3.10.1 Geometry Tool Reports3.10.2 Workmanship3.10.3 Pipeline Internal Inspection Operations3.10.3.1 General3.10.3.2 Preparatory Work3.10.3.3 Pig Load A
13、nd Launch3.10.3.4 Pipeline Operation During Pigging3.10.3.5 Brush and Gauging Survey3.10.3.6 Geometry Survey3.10.3.7 Pipe Wall Thickness Survey3.10.3.8 Lost Pig- End of Section Table of Contents -SECTION 33 52 43.13 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without l
14、icense from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-33 52 43.13 (February 2010)-Preparing Activity: USACEUNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION 33 52 43.13AVIATION FUEL PIPING02/10*NOTE: This guide specification covers the requireme
15、nts for piping and valves for aircraft refueling systems constructed to the requirements of the DoD Type III/IV/V, and Cutn Cover Hydrant Refueling System Standards. DoD Type III systems shall conform to Standard Design 078-24-28 PRESSURIZED HYDRANT FUELING SYSTEM (TYPE III). DoD Type IV/V systems s
16、hall conform to Standard Design 078-24-29 AIRCRAFT DIRECT FUELING SYSTEM (TYPE IV) DESIGN.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and re
17、quirements not required in respective project, whether or not brackets are present.Comments and suggestion on this specification are welcome and should be directed to the technical proponent of the specification. A listing of the technical proponents, including their organization designation and tel
18、ephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL1.1 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by bas
19、ic designation only and listed in this paragraph by organization, designation, date, SECTION 33 52 43.13 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-and title.Use the Reference Wizards Check Reference feature when you add a RID outside of t
20、he Sections Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizards Check Reference feature to update the issue dates.References not used in the text will automatically be deleted from this section of the project specification when you choose t
21、o reconcile references in the publish print process.*The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.AMERICAN PETROLEUM INSTITUTE (API)API RP 1110 (2007) Pressure Testing of Steel Pipelin
22、es for the Transportation of Gas, Highly Volatile Liquids or Carbon DioxideAPI RP 582 (2009) Welding Guidelines for the Chemical, Oil, and Gas IndustriesAPI STD 600 (2009; Errata 2009) Steel Gate Valves-Flanged and Butt-welding Ends, Bolted BonnetsAPI STD 608 (2008) Metal Ball Valves - Flanged, Thre
23、aded, And Welding EndAPI Spec 5L (2007; Errata 2009) Specification for Line PipeAPI Spec 6D (2008; Errata 2008; Errata 2008; Errata 2009; Addendum 2009) Specification for Pipeline ValvesAPI Spec 6FA (1999; R 2006; Errata 2006; Errata 2008) Specification for Fire Test for ValvesAPI Std 1529 (2005) Av
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS335243132010AVIATIONFUELPIPING 航空 燃油 管路 PDF

链接地址:http://www.mydoc123.com/p-449764.html