1、MILITARY SPECIFICATION CASE, TELESCOPE: M164 Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-MIL-C-60255 12 m 9999906 033714b m MIL-C-60255 (Mu) 3.5 Per
2、f ormance. 3.5.1 Strap.- The strap shall withstand a direct pull of 20 pounds, subsequent to which it shall remain secure and show no evidence of damage. 3.5.2 Fasteners.- The catches shall function without inter- ference and, when secured, they shall lock the lid to the body and show no evid.ence o
3、f looseness. 3.5.3 u- The lid shall fit true and even and shall open and close easily without restriction or binding. 3.5.4 Pads and gasket.- The pads shall be securely cemented to the lid and body and the gasket shall be securely cemented to the lid. Pads and gasket shall show no evidence of damage
4、 or looseness. 4. QUALITY ASSURANCE PROVISIONS 4.1 Responsibility for inspection.- Unless otherwise specified in the contract or purchase order, the supplier is responsible for the performance of all inspection requirements as specified herein. Except as-otherwise specified, the supplier may utilize
5、 his own facilities or any commercial laboratory acceptable to the Government. The Government reserves the right to perform any of the inspections set forth in the specification where such inspections are deemed necessary to assure supplies and services conform to prescribed requirements. 4.1.1 Gene
6、ral provisions.- The component and subassembly in- spection requirements of MIL-F-13926 form a part of the Quality Assurance Provisions of this specification. Definitions of inspection terms shall be as listed in MIL-STD-109. 4.2 Initial production test.- Initial production test samples shall be sub
7、mitted in accordance with contract requirements. otherwise specified in the contract, samples shall be the first two pro- duction units and shall have been manufactured using the same materials, processes, and procedures as will be used in regular production. Ini- tial production testing shall be in
8、 accordance with 4.3, 4.4, and 4.6 and shall be witnessed by the Government representative for all examina- tions and tests. The Government reserves the right to conduct any or all examinations or tests as may be deemed necessary. Unless 4.2.1 Initial production sample failure.- Should one unit fail
9、 to meet the initial production testing specified in 4.2, the contractor shall cease those operations which are causing the rejection and make the necessary corrections thereto. When corrections in the process or controls have been made, two additional (new) production models shall be submitted in a
10、ccordance with 4.2. 4.3 Inspection provisions. 3. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-MIL-C-bo255 12 W 7777706 0337347 T W MIL-C-60255 (MU) 4,3.1 Submission of product.- Unless otherwise specified by the Contracting Officer, inspection lo
11、t size, lot formation, and pre- sentation of lots shall be in accordance with “Submission of Product“ provisions of MIL-STD-105. shall be inspected in accordance with the inspection provisions contained in MIL-F-13926. Examinations and tests related to Section 3 herein shall be performed on a single
12、 defect (individual characteristic) basis in accordance with MIL-STD-105 and the sampling plans specified in Tables I, II, and III herein. Examinations and tests for packaging, packing, and marking shall be in accordance with MIL-P-14232 and Section 5 here- in. The tabulated classification of defect
13、s shall constitute the mini- mum inspection to be performed by the supplier prior to Government acceptance or rejection by lot. 4,3.2 Examinakkm and tests,- Components and subassemblies TABLE 1 - CLASSIFICATION OF DEFECTS CLASS CHARACTERISTIC REQUIREMENT TEST PROCEDURE CRITICAL : NONE - MAJOR: AQL 2
14、.5% Defective 101. Strap 102. Fasteners 103, Lid 104. Pads and gasket 3.5.1 4.6.2.1 3.5.2 4.6.2.2 3.5.3 4.6.2.3 3.5.4 4.6.264 - MINOR: NONE 4.3.3 Acceptance and rejection.- Rejected lots shall be screened for all defective characteristics. Removal or correction of defective units and resubmittance o
15、f rejected lots shall be in accordance with “Acceptance and Rejection“ as specified in MIL-STD-105. 4.4 Special sampling. 4.4.1 General.- One case shall be selected at random as a special sampling from each 100 produced. quirements and tests in Table II. The sample shall meet the re- TABLE II CHARAC
16、TERISTIC REQUIREMENT TEST PROCEDURE 301. Fabrication 3.2 Applicable drawings - 302. General specification 3.3 MIL-F-13926 - visual 4.4.2 Environmental.- Three cases shall be selected at random visual as samples from each 50 produced, or from each months production, whichever occurs first. Each sampl
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYMILC602551965CASETELESCOPEM164M164 望远镜 PDF

链接地址:http://www.mydoc123.com/p-441911.html