1、PMP 资格认证考试-项目成本管理(三)及答案解析(总分:20.00,做题时间:90 分钟)一、B单项选择题/B(总题数:20,分数:20.00)1.Estimating cost can be best described by which of the following _. A. the process of developing the future trend along with the assessment of probabilities, uncertainties, and inflation that could occur during the project B.
2、the process of assembling and predicting costs of a project over its life cycle C. the process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed D. the process of gathering, accumulating, analyzing, monitoring, reporti
3、ng, and managing the costs on an on-going basis(分数:1.00)A.B.C.D.2.What is the purpose of the work breakdown structure (WBS)? A. The WBS allows the project managers to delegate responsibility of all of the project activities. B. The WBS is a narrative description of the work required for the project.
4、 C. The WBS describes the total program as a summation of subdivided elements. D. The WBS is a statement of what will be made, how many units will be made, and when they will be made.(分数:1.00)A.B.C.D.3.Which type of project cost estimate is the most accurate? A. Preliminary. B. Definitive. C. Order
5、of magnitude. D. Conceptual.(分数:1.00)A.B.C.D.4.Which of the following type of contracts is most preferable to the contractor doing the project work? A. Cost plus fixed fee. B. Fixed price. C. Fixed price and incentive fee. D. B and C.(分数:1.00)A.B.C.D.5.To assist in budget control, it is suggested th
6、at the estimate occur at the _ level of the WBS. A. highest B. lowest C. major work effort D. third(分数:1.00)A.B.C.D.6.Cost Variance (CV) is which of the following equations? A. CV=BCWPBCWS B. CV=BCWPACWP C. CV=SV/BCWS D. A and C(分数:1.00)A.B.C.D.7.In the following table, which project is most likely
7、to finish ahead of schedule? A. Project A B. Project B C. Project C D. All three the projects will be completed at the same time ProjectBCWSBCWPACWPABC1000100010008006001200600800800(分数:1.00)A.B.C.D.8.Based the information in question 7, which will most likely be completed within time and cost const
8、raints?A) Project A. B) Project B. C. Project C. D. Both A and B answers.(分数:1.00)A.B.C.D.9.Determining buget can he best described by which of the following? A. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could occur duri
9、ng the project. B. The process of assembling and predicting costs of a project over its life cycle. C. The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed. D. The process of gathering, accumulating, analyzing
10、, monitoring, reporting, and managing the costs on an on-going basis.(分数:1.00)A.B.C.D.10.Which of the following is a direct project cost? A. Lighting and heating for the corporate office. B. Workers compensation insurance. C. Piping for an irrigation project. D. A and B.(分数:1.00)A.B.C.D.11.Controlin
11、g cost can be best described by which of the following? A. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could occur during the project. B. The process of assembling and predicting costs of a project over its life cycle. C.
12、The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed. D. The process of gathering, accumulating, analyzing, monitoring, reporting, and managing the costs on an on-going basis;(分数:1.00)A.B.C.D.12.Which one of t
13、he following is NOT a trade-off decision that must be made in the development of the project plan? A. Whether to use skilled or unskilled laborers. B. The amount of profit vendors should make versus the profit other vendors have received in the past. C. Manufacturing in-house or sub-contracting out
14、the work. D. The important of cost versus quality.(分数:1.00)A.B.C.D.13.The BCWS=$250, the ACWP=$350, and the BCWP=$200. Calculate the Cost Variance A. -$150 B. $150 C. -$50 D. $50(分数:1.00)A.B.C.D.14.One of the types of cost estimation is Order of Magnitude. This estimate _. A. is performed when detai
15、led information is available B. is performed when little if any information is available C. is used in the beginning of the project conceptualization D. B and C(分数:1.00)A.B.C.D.15.In a fixed price contract which of the following holds true? A. The seller agrees to use his best effort to fulfill the
16、contract within the estimated contract amount. B. The seller agrees to perform a service or furnish supplies at the established contract price. C. If the amount of the contract is exceeded the seller is not obligated to perform further unless the buyer increases the funds. D. More risks are placed o
17、n the buyer.(分数:1.00)A.B.C.D.16.If the project was supposed to have $1000 worth of work accomplished, but only completed $850 worth of work, what is the Scheduled Variance? A. $150. B. $1500. C. Cannot calculate from the information provided. D. -$150.(分数:1.00)A.B.C.D.17.If $ 850 worth of work is co
18、mpleted, but it actually cost $ 900 to perform the work, what is the Cost Variances? A. $5O. B. -$50. C. Cannot calculate from the provided information. D. $150.(分数:1.00)A.B.C.D.18.Life Cycle Costing is a term that is _. A. used when making decisions between alternatives B. employed principally by t
19、he government C. typically used in the construction industry D. A and B(分数:1.00)A.B.C.D.19.The four types of costs that are found in the Life Cycle Costing concept are _. A. operating/maintenance, discard, direct, and variable B. indirect, auxiliary, development, and production C. operating/maintena
20、nce, development, discard, and production D. indirect, auxiliary, indirect, and direct(分数:1.00)A.B.C.D.20.Jake purchases a piece of equipment in March, asking to have it be delivered in ten days. Since it is past mid-month, Jake knows the debate will not invoice him for approximately 45 days. How sh
21、ould he record this expenditure in his monthly management accruals vs. budget reports for March? A. Include the cost of the equipment because it is a known, committed expense in March. B. Do not include the cost of the equipment because it will not be delivered in March. C. Recognize the expense in
22、May when the invoice arrives. D. Recognize the expense when the invoice is processed in June.(分数:1.00)A.B.C.D.PMP 资格认证考试-项目成本管理(三)答案解析(总分:20.00,做题时间:90 分钟)一、B单项选择题/B(总题数:20,分数:20.00)1.Estimating cost can be best described by which of the following _. A. the process of developing the future trend alo
23、ng with the assessment of probabilities, uncertainties, and inflation that could occur during the project B. the process of assembling and predicting costs of a project over its life cycle C. the process of establishing budgets, standards, and a monitoring system by which the investment cost of the
24、project can be measured and managed D. the process of gathering, accumulating, analyzing, monitoring, reporting, and managing the costs on an on-going basis(分数:1.00)A.B. C.D.解析:估算成本的最佳解释是_。 A) 是一个未来趋势的完成过程,这个过程包括项目期间对概率、不确定性和通货膨胀的评估 B) 在整个项目生命周期内项目成本整理和预测的过程 C) 是一个确定预算,标准和监控系统的过程,通过这个系统可以管理测量项目成本投入
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 成本 管理 答案 解析 DOC