VA 26 08 00-2010 COMMISSIONING OF ELECTRICAL SYSTEMS.pdf
《VA 26 08 00-2010 COMMISSIONING OF ELECTRICAL SYSTEMS.pdf》由会员分享,可在线阅读,更多相关《VA 26 08 00-2010 COMMISSIONING OF ELECTRICAL SYSTEMS.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、07-10 26 08 00 - 1 SECTION 26 08 00 COMMISSIONING OF ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION A. The requirements of this Section apply to all sections of Division 26. B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commis
2、sioned are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. A Commissioning Agent (CxA) appointed by the Department of Veterans Affairs will
3、manage the commissioning process. 1.2 RELATED WORK A. Section 01 00 00 GENERAL REQUIREMENTS. B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. 1.3 SUMMARY A. This Section includes requirements for commissioning the electrical system
4、s, subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. B. The commissioning activities have been developed to support the VA requirements to meet guidelines for Federal Leadership in Environmental, Energy, and
5、Economic Performance. SPEC WRITER NOTE: Paragraph C is for LEED projects. Delete paragraph or subparagraphs as necessary for specific projects. C. The commissioning activities have been developed to support the United States Green Building Council (USGBC) LEED rating program and to support delivery
6、of project performance in accordance with the Contract Documents developed with the approval of the VA. 1. Commissioning activities and documentation for the LEED section on “Energy and Atmosphere” prerequisite of “Fundamental Building Systems Commissioning”. 2. Commissioning activities and document
7、ation for the LEED section on “Energy and Atmosphere” requirements for the “Enhanced Building System Commissioning” credit. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-07-10 26 08 00 - 2 3. Activities and documentation for the LEED section on “Me
8、asurement and Verification” requirements for the Measurement and Verification credit. D. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more specifics regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members. 1.4 DEFINITIONS A. Ref
9、er to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions. 1.5 COMMISSIONED SYSTEMS A. Commissioning of a system or systems specified in this Division is part of the construction process. Documentation and testing of these systems, as well as training of the VAs Operation and Mainten
10、ance personnel, is required in cooperation with the VA and the Commissioning Agent. SPEC WRITER NOTE: Paragraph B should list the specific systems that will be commissioned. Edit the list as necessary for specific projects. The list below should match the list included in Section 01 91 00 GENERAL CO
11、MMISSIONING REQUIREMENTS. It is recommended that the list included in Section 01 91 00 be developed first and then copied/pasted into the list below. Both lists should be identical to prevent confusion. B. The following Electrical systems will be commissioned: 1. Utility Service Entrance Switchgear
12、(Fuses and circuit breaker settings, metering, mimic diagram, gages, and controls). 2. Standby Generator Systems (Automatic transfer switches, fuel delivery pumps and motors, battery charging and instrumentation, muffler and exhaust system, and vibration isolation). 3. Generator Paralleling Switchbo
13、ards (Automatic transfer switches, instrumentation, metering and gages, and controls). 4. Generator Power Distribution Systems (Fuses and circuit breaker settings, metering, gages, and controls). 5. Utility Power Unit Substations (Transformers and tap settings, fuses and circuit breaker settings, me
14、tering, gages, and controls). 6. Generator Power Unit Substations (Transformers and tap settings, fuses and circuit breaker settings, metering, gages, and controls). 7. Automatic Transfer Switches (Test with associated generator). Provided by IHSNot for ResaleNo reproduction or networking permitted
15、without license from IHS-,-,-07-10 26 08 00 - 3 8. Normal Power Distribution Systems (Grounding tests, coordination study review, major circuit breaker settings, meters and gages, and controls). 9. Life Safety Power Distribution Systems (Automatic transfer on loss of normal power, grounding tests, c
16、oordination study review, major circuit breaker settings, meters and gages, and controls). 10. Critical Power Distribution Systems (Automatic transfer on loss of normal power, grounding tests, coordination study review, major circuit breaker settings, meters and gages, and controls). 11. Essential E
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- VA2608002010COMMISSIONINGOFELECTRICALSYSTEMSPDF

链接地址:http://www.mydoc123.com/p-1074950.html