1、05-01-12 01 32 16.16 - 1 SECTION 01 32 16.16 NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) SPEC WRITER NOTES: 1. Coordinate this Design-Build Specification with FAR 52.232, VAAR 852.236 and Section 01 00 00, GENERAL REQUIREMENTS; and Section 00 11 21, REQUEST FOR PROPOSALS TO DESIGN-BUILD (RFPDB).
2、Specifically: Article SCHEDULE OF PAYMENTS FOR DESIGN SERVICES, Article OPERATIONS AND STORAGE AREAS, Paragraph “Phasing” in Section 01 00 00, GENERAL REQUIREMENTS; and Articles A2.C; C3.A.3; D1.A; and D1.B in Section 00 11 21, REQUEST FOR PROPOSALS TO DESIGN-BUILD (RFPDB). 2. Delete between / - / i
3、f not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs. PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Network Analysis System (NAS) plan and schedule demonstrating fulfillment of the contract requirements, s
4、hall keep the network up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM)
5、Precedence Diagramming Method (PDM) technique will be utilized to satisfy both time and cost applications. All schedule data and reports required under this specification section shall be based upon regular total float, not relative total float schedules. 1.2 CONTRACTORS REPRESENTATIVE: A. The Contr
6、actor shall designate an authorized representative in the firm who will be responsible for the preparation of the network diagram, review and report progress of the project with and to the Contracting Officers representative. B. The Contractors representative shall have direct project control and co
7、mplete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section and such authority shall not be interrupted throughout the duration of the project. 1.3 CONTRACTORS CONSULTANT: A. To prepare the network diagram, and compact disk(s), which reflects the
8、Contractors project plan, the Contractor shall engage an independent Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-01-12 01 32 16.16 - 2 CPM consultant who is skilled in the time and cost application of scheduling using (PDM) network techniques
9、for construction projects, the cost of which is included in the Contractors bid. This consultant shall not have any financial or business ties to the Contractor, and shall not be an affiliate or subsidiary company of the Contractor, and shall not be employed by an affiliate or subsidiary company of
10、the Contractor. B. / (i) Prior to engaging a consultant, and within 10 calendar days after award of the contract, / (ii) With the initial cost proposal, / (iii) With the initial response to the RFP / the Contractor shall submit to the Contracting Officer: 1. The name and address of the proposed cons
11、ultant. 2. Sufficient information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph. 3. A list of prior construction projects, along with selected PDM network diagram samples on current projects which the proposed consultant has
12、 performed complete project scheduling services. These network diagram samples must show complete project planning for a project of similar size and scope as covered under this contract. C. The Contracting Officer has the right to approve or disapprove employment of the proposed consultant, and will
13、 notify the Contractor of the VA decision within seven calendar days from receipt of information. In case of disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration. The Contractor must have their CPM Consultant approved prior to / (i) submitti
14、ng any diagram, (ii) completion of contract negotiations, (iii) submission of their best and final offer./ 1.4 COMPUTER PRODUCED SCHEDULES A. The contractor shall provide to the VA monthly computer processing of all computer-produced time/cost schedules and reports generated from monthly project upd
15、ates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of Primavera (P6) to the contracting officers representative; a hard copy listing of all project schedule changes, and associated data, ma
16、de at the update and an electronic file of this data in Primavera (P6) batch format; and the resulting monthly updated schedule in a compressed electronic file in Primavera (P6), (PDM) format. These must be submitted with and substantively support the contractors monthly payment request and the sign
17、ed lookahead report. The resident engineer shall identify the five Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-01-12 01 32 16.16 - 3 different report formats that the contractor shall provide based upon the monthly schedule updates. B. The con
18、tractor is responsible for the correctness and timeliness of the computer-produced reports. The Contractor is also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified. C. Th
19、e VA shall report errors in computer-produced reports to the Contractors representative within ten calendar days from receipt of reports. The Contractor will reprocess the computer-produced reports and associated compact disk(s), when requested by the Contracting Officers representative, to correct
20、errors which affect the payment and schedule for the project. 1.5 THE INTERIM PROJECT NETWORK DIAGRAM SUBMITTAL A. Interim Diagram Submittal: Within 21 calendar days after receipt of Notice to Proceed, the Contractor shall submit for the Contracting Officers review; three blue line copies of the int
21、erim network diagram on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in a compressed Primavera (P6), (PDM) format. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data
22、, including event cost. Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, duration, predecessor and successor relationships, trade code, area code, description, budget amount, early start date, early finish date, late start date,
23、 late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start and start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Offi
24、cer. The contractor shall make a separate written detailed request to the Contracting Officer identifying these date constraints and secure the Contracting Officers written approval before incorporating them into the network diagram. The Contracting Officers separate approval of the interim network
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- VA013216162012NETWORKANALYSISSCHEDULESDESIGNBUILDONLYPDF

链接地址:http://www.mydoc123.com/p-1074654.html