1、01-11 01 32 16.01 - 1 SECTION 01 32 16.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES PART 1- GENERAL 1.1 DESCRIPTION: The Architect/Engineer of Record (A/E) shall develop a Critical Path Method (CPM Schedule) plan and schedule demonstrating fulfillment of the contract requirements as designated in
2、VA PG 18-15, shall keep the CPM up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract. Conventional Critical Path Method (CPM) Precedence Diagramming Method (PDM) technique will be utilized to sa
3、tisfy both time and cost applications. All schedule data and reports required under this specification section shall be based upon regular total float, not relative total float schedules. 1.2 A/ES REPRESENTATIVE: A. The A/E shall designate an authorized representative in the firm who will be respons
4、ible for the preparation of the CPM Schedule, review and report progress of the project with and to the Project Manager and the Contracting Officer. B. The A/Es representative shall have direct project control and complete authority to act on behalf of the A/E in fulfilling the requirements of this
5、specification section and such authority shall not be interrupted throughout the duration of the project. 1.3 A/ES SCHEDULE PREPARATION: A. To prepare the CPM Schedule, and subsequent periodic updates, which reflects the A/Es project plan, the A/E shall either designate a qualified individual within
6、 their firm or engage an independent CPM consultant (CPM Developer) who is skilled in the time and cost application of scheduling using (PDM) network techniques for Design projects, the cost of which is included in the A/Es bid. B. Within 10 calendar days after award of the contract, the A/E shall s
7、ubmit to the Contracting Officer: 1. The name of the CPM Developer. 2. The Computer Software to be utilized. 3. Sufficient information to show that the CPM Developer has the qualifications to meet the requirements specified in the preceding paragraph. C. The Contracting Officer has the right to appr
8、ove or disapprove the designated CPM developer, and will notify the A/E of the VA decision Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-01-11 01 32 16.01 - 2 within seven calendar days from receipt of information. In case of disapproval, the A/E s
9、hall resubmit another CPM Developer within 10 calendar days for renewed consideration. The A/E must have their CPM Developer approved prior to submitting the Initial CPM Schedule 1.4 COMPUTER PRODUCED SCHEDULES A. The A/E shall provide to the VA Project Manager, Contracting Officer and CPM Schedule
10、Analyst, monthly computer processing of all computer-produced time/cost schedules and reports generated from monthly project updates. A hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data. These reports shall be submitted wit
11、h and substantively support the A/Es monthly payment request. The Project Manager shall identify the different report formats that the A/E shall provide based upon the monthly schedule updates. B. The A/E is responsible for the correctness and timeliness of the computer-produced reports. The A/E is
12、also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified. C. The VA shall report errors in computer-produced reports to the A/Es representative within ten calendar days from
13、 receipt of reports. The A/E will reprocess the computer-produced reports and associated compact disk(s), when requested by the Contracting Officers representative, to correct errors which affect the payment and schedule for the project. 1.5 THE COMPLETE CPM SCHEDULE SUBMITTAL A. Within 45 calendar
14、days after receipt of Notice to Proceed, the A/E shall submit for the Project Manager and Contracting Officers review; three blue line copies of the complete CPM Schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file, (PDM) format. The submittal shall also include three co
15、pies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost. Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, duration, predecessor and successor
16、relationships, area code, description, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start and start-to-start without lead or lag constraints. Activity/event date constraints,
17、not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer. The A/E shall make Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-01-11 01 32 16.01 - 3 a separate written detailed request to the Contra
18、cting Officer identifying these date constraints and secure the Contracting Officers written approval before incorporating them into the CPM Schedule. The Contracting Officers separate approval of the CPM Schedule shall not excuse the A/E of this requirement. Logic events (non-work) will be permitte
19、d where necessary to reflect proper logic among work events, but must have zero duration. The complete working CPM Schedule shall reflect the A/Es approach to scheduling the complete project. The final CPM Schedule in its original form shall contain no contract modifications or changes which may hav
20、e been incurred during the final CPM Schedule development period and shall reflect the entire contract duration as defined in the bid documents. These changes/delays shall be entered at the first update after the final CPM Schedule has been approved. The A/E should provide their requests for time an
21、d supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT COMPLETION. B. Within 30 calendar days after receipt of the complete project CPM Schedule, the Project Manager of Contracting Offic
22、er will do one or both of the following: 1. Notify the A/E concerning his actions, opinions, and objections. 2. A meeting with the A/E at or near the job site for joint review, correction or adjustment of the proposed plan will be scheduled if required. Within 14 calendar days after the joint review
23、, the A/E shall revise and shall submit three blue line copies of the revised CPM Schedule, three copies of the revised computer-produced activity/event ID schedule and a revised electronic file as specified by the Contracting Officer. The revised submission will be reviewed by the Contracting Offic
24、er and, if found to be as previously agreed upon, will be approved. C. The approved baseline CPM Schedule and the corresponding computer-produced schedule(s) shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section. 1.6 WORK ACTIV
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- VA013216012011ARCHITECTURALANDENGINEERINGCPMSCHEDULESPDF

链接地址:http://www.mydoc123.com/p-1074651.html