UL SUBJECT 2262-2012 OUTLINE OF INVESTIGATION FOR FUEL CELL MODULES FOR USE IN PORTABLE AND STATIONARY EQUIPMENT (Issue 2)《用于便携式和固定设备的燃料电池组件的调查大纲 (议题2)》.pdf
《UL SUBJECT 2262-2012 OUTLINE OF INVESTIGATION FOR FUEL CELL MODULES FOR USE IN PORTABLE AND STATIONARY EQUIPMENT (Issue 2)《用于便携式和固定设备的燃料电池组件的调查大纲 (议题2)》.pdf》由会员分享,可在线阅读,更多相关《UL SUBJECT 2262-2012 OUTLINE OF INVESTIGATION FOR FUEL CELL MODULES FOR USE IN PORTABLE AND STATIONARY EQUIPMENT (Issue 2)《用于便携式和固定设备的燃料电池组件的调查大纲 (议题2)》.pdf(12页珍藏版)》请在麦多课文档分享上搜索。
1、UL COPYRIGHTED MATERIAL NOT AUTHORIZED FOR FURTHER REPRODUCTION ORDISTRIBUTION WITHOUT PERMISSION FROM ULAugust 20, 20121UL 2262OUTLINE OF INVESTIGATIONFORFUEL CELL MODULES FOR USE IN PORTABLE AND STATIONARYEQUIPMENTIssue Number 2AUGUST 20, 2012Summary of TopicsThis is the second issue of the Outlin
2、e of Investigation for Fuel CellModules for Use in Portable and Stationary Equipment. Note that the firstissue of the outline was named Portable Proton Exchange Membrane(PEM) Type Fuel Cell Power Plants With Or Without Uninterruptable PowerSupply (UPS) Features And Portable Proton Exchange Membrane
3、(PEM)Type Fuel Cell Modules For Factory Installation In Original EquipmentManufacturer (OEM) Type Equipment For Indoor Use.COPYRIGHT 2012 UNDERWRITERS LABORATORIES INC.UL COPYRIGHTED MATERIAL NOT AUTHORIZED FOR FURTHER REPRODUCTION ORDISTRIBUTION WITHOUT PERMISSION FROM ULAUGUST 20, 2012UL 22622No T
4、ext on This PageUL COPYRIGHTED MATERIAL NOT AUTHORIZED FOR FURTHER REPRODUCTION ORDISTRIBUTION WITHOUT PERMISSION FROM ULCONTENTSINTRODUCTION1 Scope .42 Units of Measurement .43 References and Components .44 Glossary .4CONSTRUCTION5 General 46 Terminals and Electrical Connections 5PERFORMANCE7 Gener
5、al 58 Conductivity Test (Non-Metallic Tubing) 59 Accumulation of Static Electricity (Non-Metallic Tubing) 610 Adhesive Label Tests 611 Production Testing 7MARKINGS12 Markings and Instructions .7APPENDIX AStandards for ComponentsA1APPENDIX BAUGUST 20, 2012 UL 2262 3UL COPYRIGHTED MATERIAL NOT AUTHORI
6、ZED FOR FURTHER REPRODUCTION ORDISTRIBUTION WITHOUT PERMISSION FROM ULINTRODUCTION1 Scope1.1 These requirements cover component fuel cell modules for building into equipment, including portableand stationary fuel cell applications.1.2 These requirements also cover proton exchange membrane (PEM), alk
7、aline, phosphoric acid, moltencarbonate, solid oxide type fuel cell modules that are intended to be factory installed in complete products.1.3 These requirements do not cover removable fuel cartridges for refueling the fuel cell module.2 Units of Measurement2.1 Values stated without parentheses are
8、the requirement. Values in parentheses are explanatory orapproximate information.3 References and Components3.1 Any undated reference to a code or standard appearing in the requirements of this Outline ofInvestigation shall be interpreted as referring to the latest edition of the code or standard.3.
9、2 A component of a product covered by this outline of investigation shall comply with the requirementsfor that component. See Appendix A for a list of standards covering components generally used in theproducts covered by this outline.3.3 The normative references of Clause 2 of the Standard for Fuel
10、 cell technologies Part 2: Fuel cellmodules, IEC 62282-2, apply to this outline except as noted in Appendix B.4 Glossary4.1 Terms and definitions as outlined in Clause 3 of the Standard for Fuel cell technologies Part 2: Fuelcell modules, IEC 62282-2, apply to this outline.CONSTRUCTION5 General5.1 T
11、he requirements outlined in Clause 4 of the Standard for Fuel cell technologies Part 2: Fuel cellmodules, IEC 62282-2, apply to this outline except where noted elsewhere.AUGUST 20, 2012UL 22624UL COPYRIGHTED MATERIAL NOT AUTHORIZED FOR FURTHER REPRODUCTION ORDISTRIBUTION WITHOUT PERMISSION FROM UL6
12、Terminals and Electrical Connections6.1 Terminals and electric connections in the fuel cell module shall comply with the requirements forterminals and connectors as outlined in the Standard for Information Technology Equipment Safety Part1: General Requirements, UL 60950-1.PERFORMANCE7 General7.1 Th
13、e fuel cell modules shall comply with the applicable Type tests of Clause 5 of the Standard for Fuelcell technologies Part 2: Fuel cell modules, IEC 62282-2, and as noted in Sections811.7.2 The test voltage values outlined in Table 1 under the dielectric strength test of Clause 5.7 of theStandard fo
14、r Fuel cell technologies Part 2: Fuel cell modules, IEC 62282-2, are to be replaced by valuesin accordance with Section 5.2 electric strength test of the Standard for Information TechnologyEquipment Safety Part 1: General Requirements, UL 60950-1.8 Conductivity Test (Non-Metallic Tubing)8.1 This tes
15、t is conducted to determine compliance of non-metallic piping systems to Clause 4.2.6.1 ofthe Standard for Fuel cell technologies Part 2: Fuel cell modules, IEC 62282-2, when employingnon-metallic piping system materials that are conductive.8.2 The non-metallic piping/tubing materials are determined
16、 to comply if when tested as outlined in 8.3 8.7, the measured resistance does not exceed 1 M.8.3 Three samples of the non-metallic piping/tubing are to be provided with conductive pads at variouslocations on the samples. The pads are to be located at:a) Points as far away as possible from the point
17、s at which the tubing is mounted to groundedmetal,b) Intermediate points, andc) Other points that result in high resistance to ground because of the configuration of thetubing being tested.8.4 The conductive pads are to be metal foil approximately 2 cm2, and attached to the samples by a thinfilm of
18、petrolatum or similar material.8.5 Ground point electrodes are to be provided on the samples at a point or points on the part where itis mounted to grounded metal; for example, the ground point electrode on a non-metallic tubing shallconsist of metal fittings installed on the ends of the tubing for
19、connection to grounded parts.8.6 The resistance is to be measured between the ground point electrodes (i.e. metal tube fittings) andthe conductive pads after the samples have been conditioned for at least 48 h at a relative humidity of50% 1%.AUGUST 20, 2012 UL 2262 5UL COPYRIGHTED MATERIAL NOT AUTHO
20、RIZED FOR FURTHER REPRODUCTION ORDISTRIBUTION WITHOUT PERMISSION FROM UL8.7 The resistance is to be measured with an ohmmeter that has an effective internal resistance of 100000 10 000 . The open-circuit potential shall be 1 000 V d.c. and the short-circuit current shall be 5mA.9 Accumulation of Sta
21、tic Electricity (Non-Metallic Tubing)9.1 This test is conducted to determine compliance of non-metallic piping systems to Clause 4.2.6.1 ofthe Standard for Fuel cell technologies Part 2: Fuel cell modules, IEC 62282-2, when employingmaterials that are not conductive but that are designed to avoid st
22、atic charge build up.9.2 The non-metallic piping/tubing is determined to comply if no sparks are observed when a groundedmetal sphere is brought into gradual contact with the non-metallic tubing after it has been electrostaticallycharged in accordance with the test methods outlined in 9.3 9.6.9.3 Th
23、ree samples of the tubing with ground point electrodes as described in 8.2 (i.e. metal fittings) areto be conditioned for at least 48 h at a relative humidity of 25% 10%.9.4 Immediately after removal from the low-humidity chamber, the samples are to be supported by meansof insulators in a room havin
24、g a relative humidity not more than 35% and having all sources of light, otherthan electrical sparks, eliminated.9.5 The ground point electrodes are to be grounded. An electrostatic charge is to be sprayed onnonconductive parts of the product using an electrostatic generator limited to 5 000 V.9.6 A
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ULSUBJECT22622012OUTLINEOFINVESTIGATIONFORFUELCELLMODULESFORUSEINPORTABLEANDSTATIONARYEQUIPMENTISSUE2

链接地址:http://www.mydoc123.com/p-1069252.html