SANS 10120-3 C-1982 Code of practice for use with standardized specifications for civil engineering construction and contract documents Part 3 Guidance for design Section C Site cl.pdf
《SANS 10120-3 C-1982 Code of practice for use with standardized specifications for civil engineering construction and contract documents Part 3 Guidance for design Section C Site cl.pdf》由会员分享,可在线阅读,更多相关《SANS 10120-3 C-1982 Code of practice for use with standardized specifications for civil engineering construction and contract documents Part 3 Guidance for design Section C Site cl.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、 Collection of SANS standards in electronic format (PDF) 1. Copyright This standard is available to staff members of companies that have subscribed to the complete collection of SANS standards in accordance with a formal copyright agreement. This document may reside on a CENTRAL FILE SERVER or INTRA
2、NET SYSTEM only. Unless specific permission has been granted, this document MAY NOT be sent or given to staff members from other companies or organizations. Doing so would constitute a VIOLATION of SABS copyright rules. 2. Indemnity The South African Bureau of Standards accepts no liability for any
3、damage whatsoever than may result from the use of this material or the information contain therein, irrespective of the cause and quantum thereof. SARS 0120 : Part 3 Sect ion C-1982 Site clenmnce Clause 1 . 1.1 1.1.1 1.1.2 1.1.3 1.1.4 1.2 1.2.1 1.2.2 1.3 1.3.1 1.3.2 PAUT 3 : :GUII)ANCE NlR DESIGN SE
4、CT LON G CIINTI!WS Page Number PRE-TENDER CONS1I)EMlTONS 1 Tnvestigatlons . 1 General 1 . Valuable trees 1 . Burning of trees 1 Credit for recovered material 1 . Administration 1 Indigenous forest 1 . Reclearlng of vegetation 1 Documentation 1 . Substantial structures 1 Reclearlng of vegetation 1 1.
5、3.3 Landscape preservation and consewat Lon 01 flora 1.7.4 Additional project speci Eica t ion clauses . 1.3.5 Varying hush aid vega tat ion drns lt ies 1.3.6 Measurement of tilt- clearing of erecs OF girth exceeding 1 . area cleared . 1.3.7 Clearing str Lpping. and conservation of topsoil 1.3.8 Dis
6、mantling and removal of pipelines. cables. etc m on the basil 1.3.9 Credit Eor recovered mnterial ? 2 . DESIGN REQUIREMENTS ? 2.1 Topsoil 2 . 3 . APPLICARII.T.1Y OF OTtlER COIXS 2 4 . TEST PR0CEI)LJRES ? . 5 . QUALIZY CONTROL AND OTHER CONS1I)EKKPIONS 2 First RevisIon May 1982 This wct Lnn of the co
7、de supersetler; SARS 0120 : Part 7 : Scct Ion (:-l980 SAW 0120 : Part 3 Sect ion C-1982 Site clearance NOTE: The clause number(s) given at the beginning or arter the heading of a clause islare, unless otherwise stated, the number(s) of the relevant clause(s) of SARS l200 C. PRE-TENDER CONSIIX RATION
8、S General. Although site clearance is a minor port ion of most construction contracts, the costs of clearance can become disproportionately high if the work to be carried out is not scheduled in such a way that advantage is taken OF the wide variation that exists between tlie costs oE clearing diffe
9、rent densities and types of vegetation, and different types of structures. Ensure that preliminary investigations cover matters relevant to the project such as are dealt with in 1.1.2, 1.1.3, and 1.2.1 below. Vaiuahle Trees (Suhclause 5.2.3.3) Where clearing of the site will require the contractor t
10、o deal with trees which my be regarded as valuable hy the Department of Environment Affairs or any local authority concerned, discuss the anticipated problems with the said Department or local authority (or both) with a view to either inclding suitahle requirenents in tlie project specification or s
11、clieduling suitable items. Should this prove to Ire impracticahle, ensure that the engineer provides the contractor with the clearauce and instruct ions from the said Ilcpartment or the local authority early enoup,h to ensure that the contractnrs program is not afrected by the need to comply with Su
12、bclause 5.2.3.3 of SARS 1200 C (see also Suhclause 2.4 of Section C of Part 5 of the code). Burning of Trees. Consider fire risks an11 the rmlui rements of the Atmospheric Po1luti1,n Prevention Act, 1965 (Act 45 of 1965). and discrsb these with interested authorities before specifying destrwtion by
13、burnlng. Credit for Recovered Material. Ascertain the employers wishes in regard to recoverable material, hut ensure that he is aware of the limitatins oF such operations. Although CEQ) (V11 3.3.6) provides for credit for recovered mterial, the cost and risks to the contractor during recovery and di
14、sposal may outweigh any benefits, unless the contractor operates in the scrap market or the materials to be recovered have a high intrinsic value, scli as rails from a demolished raiiway line. The party who may benefit most from the recovery of used material in sound condition is the employer. It is
15、, therefore, preferable to provide items 111 the schedule for recovery and returrl to the employers store, or for re-use (at his risk) elsewhere in the project. Indigenous Forest (Subclause 5.2.3.3) Where clearing and grubbing involves the cutting down of indigenous fores t containing a sign1 Ficant
16、 number of trees witli a trunk girth of more than 200 mm, give the Director General of the Department of Environment Affairs enough notice of the intention to clear and grub such areas to afford the said Department the opportunity of identifying the trees before they are removed and of salvaging any
17、 usable timber. Reclearing OF Vegetation (Subclause 5.5 and see also 1.3.2(c) below). !here it is expected that the need for reclearing will not arise until shortly before the site is to be handed back to the employer. provision for reclearing may be omitted from the contract with a view to negotiat
18、ing a price For the work or inviting separate tenders shortly before tlie need for such reclearance arises (see Suhclause 3.2.7 of Sect ion C of Part 5 of the code). Substantial Strctirw (Subclauses 5.3 and 5.8). Where structures that are to be dcmolishrd and removed are substantial, especially in t
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- SANS101203C1982CODEOFPRACTICEFORUSEWITHSTANDARDIZEDSPECIFICATIONSFORCIVILENGINEERINGCONSTRUCTIONANDCONTRACTDOCUMENTSPART3GUIDANCEFORDESIGNSECTIONCSITECLPDF

链接地址:http://www.mydoc123.com/p-1028513.html