SAE ARP 6196-2012 Gas Turbine Engine Test Facility Audit Process《燃气轮机发动机试验设备审核流程》.pdf
《SAE ARP 6196-2012 Gas Turbine Engine Test Facility Audit Process《燃气轮机发动机试验设备审核流程》.pdf》由会员分享,可在线阅读,更多相关《SAE ARP 6196-2012 Gas Turbine Engine Test Facility Audit Process《燃气轮机发动机试验设备审核流程》.pdf(10页珍藏版)》请在麦多课文档分享上搜索。
1、_SAE Technical Standards Board Rules provide that: “This report is published by SAE to advance the state of technical and engineering sciences. The use of this report is entirely voluntary, and its applicability and suitability for any particular use, including any patent infringement arising theref
2、rom, is the sole responsibility of the user.” SAE reviews each technical report at least every five years at which time it may be revised, reaffirmed, stabilized, or cancelled. SAE invites your written comments and suggestions.Copyright 2012 SAE International All rights reserved. No part of this pub
3、lication may be reproduced, stored in a retrieval system or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of SAE. TO PLACE A DOCUMENT ORDER: Tel: 877-606-7323 (inside USA and Canada) Tel: +1 724-776-4970
4、(outside USA) Fax: 724-776-0790 Email: CustomerServicesae.org SAE WEB ADDRESS: http:/www.sae.orgSAE values your input. To provide feedback on this Technical Report, please visit http:/www.sae.org/technical/standards/ARP6196AEROSPACERECOMMENDEDPRACTICEARP6196 Issued 2012-05 Gas Turbine Engine Test Fa
5、cility Audit Process RATIONALETest facilities are frequently audited by various authorities, regulatory bodies, gas turbine engine OEMs and customers. The main purpose of the audit process is to ensure that the test cell operator/owner provides evidence that the facility is maintained in such a way
6、that it meets the requirements set by the OEM and authorizing bodies and that the test cell meets the conditions set in the correlation process. This document describes guidelines and criteria to audit a test facility both from an auditor perspective in addition to the user/owners perspective. SAE A
7、RP6196 Page 2 of 10 TABLE OF CONTENTS 1. SCOPE 32. REFERENCES 32.1 Applicable Documents 32.1.1 SAE Publications . 32.2 Other References 32.3 Definitions and Abbreviations . 33. AUDIT PROCESS IN GENERAL 43.1 General Information 43.2 Audit Intervals . 43.3 Repeat Audits 43.4 Corrective Actions . 44. S
8、PECIFIC AREAS OF ATTENTION . 54.1 Correlation and Test Equipment . 54.2 Manuals and Documentation 64.3 Procedures 64.4 Storage of Parts and Consumables 64.5 Training . 64.6 Safety 74.6.1 Facility . 74.6.2 Operation 74.7 Housekeeping . 74.8 Fuel . 74.9 Slave Equipment . 84.10 Software Maintenance 94.
9、10.1 Engine operating software (FADEC controlled engines) 94.10.2 Test Cell Operating Software (Data Acquisition System) . 95. MAINTAINING THE TEST CELL IS AUDIT PROOF 95.1 Configuration Control 95.2 Performance Trend Analysis . 95.3 Facility Maintenance and Inspection Plan 106. NOTES 10SAE ARP6196
10、Page 3 of 10 1. SCOPE This SAE Aerospace Recommended Practice provides recommendations for: the audit process in general; a list of specific areas of attention to be audited; maintaining the test facility in such a manner that it meets audit requirements. 2. REFERENCES 2.1 Applicable Documents The f
11、ollowing publications form a part of this document to the extent specified herein. The latest issue of SAE publications shall apply. The applicable issue of other publications shall be the issue in effect on the date of the purchase order. In the event of conflict between the text of this document a
12、nd references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained. 2.1.1 SAE Publications Available from SAE International, 400 Commonwealth Drive, Warrendale, PA 15096-0
13、001, Tel: 877-606-7323 (inside USA and Canada) or 724-776-4970 (outside USA), www.sae.org.ARP741 Turbofan and Turbojet Gas Turbine Engine Test Cell Correlation ARP5758 Trend Analysis for Maintaining Correlation of Gas Turbine Engine Test Cells ARP6028 Configuration Control for Maintaining Correlatio
14、n of Gas Turbine Engine Test Cells 2.2 Other References FAA Advisory Circular AC 43-207 Aviation Maintenance Management: McGraw - Hill, ISBN:0-00714251-X Jurans Quality Handbook McGraw - Hill, ISBN 0-07-034003-X ATA Specification 103, Standard for Jet Fuel Quality Control at Airports ISO 9001, Quali
15、ty management Chapter 4.0 Quality management system 2.3 Definitions and Abbreviations AUDIT: An independent, objective assurance activity, designed to assess both the effectiveness and efficiency of an organizations operations. FACILITY OPERATIONS MANUAL: Manual that describes the test cell layout,
16、organization, and operation. SLAVE EQUIPMENT: Equipment installed to the engine, solely for testing purposes, is removed after completion of test. A4A: Airlines for America formerly known as ATA: Air Transport Association of America, Inc. SAE ARP6196 Page 4 of 10 FADEC: Full Authority Digital Engine
17、 Control FOM: Facility Operations Manual OEM: Original Equipment Manufacturer PMD: Precision Measurement Devices 3. AUDIT PROCESS IN GENERAL 3.1 General Information Test facilities can be audited by: quality assurance or control from the maintenance organization; environmental, health, and safety or
18、ganizations, both from the maintenance provider as well as from the local authorities; regulatory bodies of the local government; regulatory bodies of the customer governments; customers; OEMs. 3.2 Audit Intervals The general interval for audits is 1 year, however, random audits are possible. 3.3 Re
19、peat Audits In case of findings requiring immediate follow up, repeat audits to monitor compliance of the corrective actions can be carried out. 3.4 Corrective Actions Findings by the auditor are reported by a findings report submitted within a period of 4 weeks. The findings are filed in the local
20、quality defect reporting system and a process owner/responsible person is identified. The quality defect reporting system requires: root cause identification; corrective action plan; action for related areas; preventative actions to avoid reoccurrence. SAE ARP6196 Page 5 of 10 4. SPECIFIC AREAS OF A
21、TTENTION This section provides an overview of attention areas. 4.1 Correlation and Test Equipment Date of last correlation. Current correlation books status. Type of engines the test cell is correlated for and as necessary confirming the engines being tested at the facility. All the precision measur
22、ement devices (PMDs) per the applicable engine manuals present to perform all tests and measurements required to assure conformance to specifications. All PMDs included in the calibration program. All PMDs traced to standards of which they were calibrated. Examples of such PMDs: load cells thermocou
23、ples pressure probes vibration sensors speed sensors For instrumentation calibrations in house: the necessary standards available. Standards include the OEM or vendor instrumentation calibration requirements such as test procedures, test equipment, limits and accuracy requirements. Specified calibra
24、tion intervals established for each PMD, related to the engine manual requirements or test equipment vendor requirements. In case of deviations to the engine manual requirements, approved alternate means of compliance. Records of calibrated PMDs containing repairs and accuracy tracking being maintai
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- SAEARP61962012GASTURBINEENGINETESTFACILITYAUDITPROCESS 燃气轮机 发动机 试验 设备 审核 流程 PDF

链接地址:http://www.mydoc123.com/p-1023236.html