REG NASA-LLIS-3396-2010 Lessons Learned - Dawn Ion Propulsion System (IPS).pdf
《REG NASA-LLIS-3396-2010 Lessons Learned - Dawn Ion Propulsion System (IPS).pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-3396-2010 Lessons Learned - Dawn Ion Propulsion System (IPS).pdf(2页珍藏版)》请在麦多课文档分享上搜索。
1、Public Lessons Learned Entry: 3396Lesson Info: Lesson Number: 3396 Lesson Date: 2010-04-6 Submitting Organization: JPL Submitted by: David Oberhettinger Subject: Dawn Ion Propulsion System (IPS) Lessons Learned Abstract: Although the Dawn IPS was planned for the most part as a built-to-print inherit
2、ance of the DS1 design, the Dawn project encountered significant cost and schedule escalation and technical difficulties. The IPS contractor suffered from management instability and from capabilities lost over the 6-year lag between the two projects. For relatively novel technologies, it may be nece
3、ssary to re-qualify the capabilities of the contractor as well as re-qualifying the design for the new mission application. Description of Driving Event: After its September 2007 launch, the Dawn spacecraft employed a solar-powered ion propulsion system (IPS) to gain the additional velocity needed t
4、o reach Vesta and Ceres, and it will use the IPS to spiral to a low altitude orbit around these asteroids. Compared to chemical rockets, ion engines make very efficient use of onboard fuel because the propulsive energy is derived from the sun. Solar electric propulsion (SEP) technology for navigatio
5、n beyond Earth orbit was successfully demonstrated from 1998 to 2001 by the Deep Space 1 (DS1) mission, and Dawn planned to use the same IPS design (Figures 1 and 2).Figure 1. Deep Space 1 is lifted from its work platform at NASA Kennedy Space Center, providing a close view of the IPSFigure 2. Hot f
6、ire test of the Deep Space 1 IPSThe development of the Dawn IPS by the NASA/Caltech Jet Propulsion Laboratory (JPL) proved much more difficult and expensive than expected. The principal unanticipated problem was a degraded ability to manufacture the DS1-legacy components, principally the ion thruste
7、rs and the Power Processor Units (PPUs) (References (1) and (2). The inherited DS1 components had evolved through informal engineering processes more typical of experiments than development of configuration-controlled flight hardware. Although the Dawn IPS contractor for the ion thrusters and PPUs w
8、as the same company that had built the DS1 hardware, and the Dawn thrusters and PPUs were proposed as build-to-print copies of the DS1 designs, the contractor encountered significant management and process problems in delivering the Dawn flight hardware. The contractor problems, which likely were ex
9、acerbated by the 6-year lag between these two projects, included: 1. JPL efforts to negotiate a fixed-price or incentive-based contract with the Dawn IPS contractor failed. The resultant cost-plus-fixed-fee contract was overrun by almost 100 percent, and the flight hardware was delivered 8 months la
10、te. 2. The Dawn IPS contractor for the ion thrusters believed it could reproduce the assembly processes for the DS1 thrusters, but major cost escalation during fabrication, assembly, and testing of the Dawn IPS revealed that the time lag between the two projects had degraded their capabilities. Also
11、, the vendor that fabricated the DS1 ion thruster plasma screen was no longer in business, and the vendor that performed chem-etching of the DS1 thruster grids did not bid on the Dawn thruster grids. No shock testing of the DS1 thruster had been performed except at the less critical spacecraft level
12、. 3. The DS1 PPU assembly procedures and other information needed to reproduce the hardware had not been adequately documented or retained. 4. Over the 2-1/2 years of the Dawn IPS build, the IPS contractor for the ion thrusters and PPUs cycled through four general managers and four Electric Propulsi
13、on department managers. Each upper-level manager in the contractors corporate unit was fully aware of a pending sale of the unit by the parent company. These managers were motivated to please their parent companys customers, and there were frequent delays due to reassignment of Dawn resources to the
14、se other projects. 5. A total of 40 IPS component and subsystem design reviews, plus the hardware reviews, produced a huge number of action items- 630. The number would have been more manageable had the required documents- technical requirements documents (TRDs), interface control drawings (ICDs), m
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS33962010LESSONSLEARNEDDAWNIONPROPULSIONSYSTEMIPSPDF

链接地址:http://www.mydoc123.com/p-1019425.html