1、Lessons Learned Entry: 2456 Lesson Info: z Lesson Number: 2456 z Lesson Date: 2010-02-16 z Submitting Organization: JPL z Submitted by: David Oberhettinger z POC Name: Stephen Greenberg; Pamela Brown z POC Email: Stephen.S.Greenbergjpl.nasa.gov; Pamela.R.Brownjpl.nasa.gov z POC Phone: 818-354-6306 (
2、Greenberg); 818-354-8081 (Brown) Subject: Aquarius EGSE Shipping Mishap Abstract: A shipping container holding test equipment for the Aquarius project fell off the lift gate while it was being unloaded from a truck, and caused minor injuries to personnel. The root cause was inadequate planning and c
3、oordination of the transportation task. Use trained and certified personnel and equipment for critical equipment moves, perform a dry run of the operation, ensure that System Safety is informed and involved, and integrate contingency planning into transportation plans. Description of Driving Event:
4、In May 2009, a wheeled shipping crate containing an electrical ground support equipment (EGSE) rack for the Aquarius project fell off the lift gate of a contracted commercial transportation van while being unloaded. The van was parked adjacent to the receiving dock at the NASA/Caltech Jet Propulsion
5、 Laboratory (JPL). After the crate was moved to the rear of the vehicle for unloading, the van driver/operator manipulated the incorrect control on the powered lift gate (Reference (1). (Figure 1 illustrates the lift gate control systems susceptibility to operator error.) This caused the lift gate t
6、o tilt instead of lower. The crate rolled off the lift gate and struck the ground, damaging the hinges and breaking off the lid. Only the crate directly contacted the ground, and the EGSE rack with its 2-inch thick foam padding remained secure within the crate. The shipping crate had four casters, b
7、ut the locks on the two downhill casters were unlocked during the operation. Figure 1. Lift gate control panel on the truck that was unloading Aquarius EGSE. The diagram below the image shows that the control panel is not well designed to deter operator error. (The yellow label indicates that the di
8、al on the right is a “Slider” control that positions the gate horizontally.)Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-The EGSE rack was being removed from the vehicle because it had not been approved in the final manifest for support equipment
9、to be transported to Argentina for Aquarius integration and test. Since a need to unload the EGSE shipping crate had been not identified to the project until just prior to the incident, there was insufficient time to coordinate and plan the EGSE off-load. Quality Assurance was present during the inc
10、ident, but System Safety was not notified of this unplanned unloading of Aquarius EGSE. Two individuals were injured as a result of this incident. The first struck his head on the pavement when he fell backward while avoiding the falling equipment. The other suffered a muscle strain while trying to
11、restrain the EGSE rack as it rolled off the tilted lift gate. The container and lid were then moved into the Spacecraft Assembly Facility (SAF) airlock for visual inspection. Visual inspection did not detect any equipment damage other than the detached shipping container lid, and the damaged shippin
12、g crate was replaced. The personnel were treated with basic first-aid, and then they returned to work (Reference (2). The test equipment required recalibration, full functional test, and internal visual inspection. Due to a lingering concern about possible damage, however, replacement EGSE was obtai
13、ned for use with Aquarius flight equipment (Reference (3). There exists some residual concern by the Aquarius project due to the risk posed by plans to move JPL Critical Items (JCI) from Argentina to Brazil, and from Brazil to the Vandenberg Air Force Base launch site. JPL has recently revamped the
14、process of preparing and reviewing transportation plans. The process is now reflected in the formal procedures of JPL Security, and preparation of a transportation plan is now a contractual requirement to be added to JPL subcontracts (Reference (4). Also, the JPL Project and Engineering Management C
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS24562010LESSONSLEARNEDAQUARIUSEGSESHIPPINGMISHAPPDF

链接地址:http://www.mydoc123.com/p-1019375.html