1、Lessons Learned Entry: 1336Lesson Info:a71 Lesson Number: 1336a71 Lesson Date: 2003-05-05a71 Submitting Organization: JPLa71 Submitted by: Bob Axsom/David OberhettingerSubject: Verify Flight & GSE Cables Against Unit & System Schematics Prior to Test (1998) Description of Driving Event: During integ
2、ration of the Genesis spacecraft, many flight and ground support equipment (GSE) cables were found to be electrically incompatible with spacecraft systems although they matched the cable wiring diagrams. Several times, testing had to be halted and the system analyzed for possible electrical overstre
3、ss caused by power having been applied to the wrong pins. Eventually, spacecraft testing was stopped long enough to perform a pin-by-pin comparison of the cable wiring diagrams to the latest unit and system schematics. Once this was completed, errors were identified, the cables were reworked, and th
4、e problems were resolved. The accuracy of cable wiring diagrams was a continuing problem on Genesis. Typically, cables are built by cable harness shops to the specifications provided by cable drawings and cable wiring diagrams. Cable design and fabrication may take place concurrently with the design
5、 of spacecraft black boxes. As a system design evolves and pin-out requirements change, there is a time lag before the interface control drawing (ICD) is updated and the changes flow back to the cable design and documentation. Should the cables be built to an outdated document, the first powering of
6、 a given spacecraft may cause major damage. Since the connectors still mate with their assigned receptacles, the electrical mismatches may not be apparent. Validating the cable harness configuration against unit and system schematics is a very time-consuming activity. If it is delayed until integrat
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS13362003LESSONSLEARNEDVERIFYFLIGHTGSECABLESAGAINSTUNITSYSTEMSCHEMATICSPRIORTOTEST1998PDF

链接地址:http://www.mydoc123.com/p-1018975.html