REG NASA-LLIS-1310-2002 Lessons Learned NASA MSFC Army Vortex Chamber Test Incident.pdf
《REG NASA-LLIS-1310-2002 Lessons Learned NASA MSFC Army Vortex Chamber Test Incident.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1310-2002 Lessons Learned NASA MSFC Army Vortex Chamber Test Incident.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1310Lesson Info:a71 Lesson Number: 1310a71 Lesson Date: 2002-08-25a71 Submitting Organization: MSFCa71 Submitted by: Huu TrinhSubject: NASA/MSFC Army Vortex Chamber Test Incident Description of Driving Event: On February 19, 2002, an incident occurred during the hot-fire testi
2、ng of the Army vortex thrust chamber assembly at MSFC Test Stand 115. This was the fourth hot-fire test of the hardware, but the first test flowing both LOX (liquid oxygen) and RP-1 fuel as the main propellants and GOX (gaseous oxygen) and GH2 (gaseous hydrogen) for the torch igniter. The first thre
3、e tests, which were successfully completed, were hot-fire tests of the GOX/GH2 torch igniter only. For these tests, gaseous nitrogen was flowed through the main injector. The fourth test was to characterize start up transient conditions. The objectives of the vortex chamber testing were to demonstra
4、te the feasibility of vortex chamber technology for a liquid hydrocarbon/liquid oxygen system, demonstrate several ignition techniques (torch, laser and combustion wave), demonstrate two rocket plume measurement methods (emission/absorption and Raman scattering), and characterize the chamber perform
5、ance by means of thrust measurements and species uniformity in the plume flow field. At approximately 5.3 seconds into the automated firing sequence, a catastrophic failure occurred to the test article. A redline cut initiated shutdown at that time. The facility proceeded to follow the normal shutdo
6、wn sequence, which initialized the safeguarding of the facility and test article. The area was immediately roped off with quality monitoring activities. Once the facility safeguarding was completed, it was determined that there were no injuries to personnel, and damage to the test facility was minor
7、. Most of the test article pieces were recovered and provided important information in the investigation and analysis of the incident. A timeline was constructed from the high-speed video film, control sequence data, and both the low and high-speed instrumentation. Due to the lack of a time stamp on
8、 the high-speed video, there were some inherent inaccuracies in correlating the instrumentation data timing with the video. Although all data systems were operational at the time of the incident, the over pressurization/detonation Provided by IHSNot for ResaleNo reproduction or networking permitted
9、without license from IHS-,-,-occurred very rapidly and as a result there was limited evidence of the over-pressurization in the collected data. The test article failed at the mounting bolts as well as the injector and spacer, and hardware was recovered over a large area of the test facility and near
10、by fields/woods. The scenarios developed by the incident investigation team pointed out that three significant events occurred during the start up transients: 1) surface burning of the chamber head end hardware, 2) surface burning of the injector module hardware, and 3) accumulation of propellants i
11、n the chamber. The primary cause of the incident was the propellant accumulation in the chamber during the ignition delay. The first two events are not believed to have caused the eventual over-pressurization. Lesson(s) Learned: Several lessons learned are identified from the subject incident: 1. Th
12、e excessive amount of propellants accumulated in the chamber was the main contributor to the test failure. This accumulation might have been caused by the unintended time delay in the LOX/RP-1 ignition. Consequently, the eventual ignition led to the chamber over-pressurization. a. Although GOX/GH2 t
13、orch igniters have been used in igniting LOX/RP-1 systems, the database and experience of such an igniter for the LOX/RP-1 system are limited. The use of this igniter type for LOX/RP-1 along with its location with respect to the chamber might have caused some delay time in the ignition and created t
14、he first two events as stated in the previous section. In this test sequence, LOX was injected to the chamber prior to the RP-1 injection. It has been speculated that RP-1 might have become frozen during this ignition delay. Past data indicates that frozen RP-1/LOX combustion releases an excessive e
15、nergy creating an over-pressurization in the combustion chamber. Furthermore, due to the nature of the of the vortex chamber flow field, the startup transient is not well understood. For the aforementioned reasons, a better-characterized igniter, such as TEA/TEB, should be applied.b. To detect the i
16、gnition/combustion occurrence, the vortex chamber should be monitored for an increase in pressure. The value of this increase and the detection duration depend on individual test conditions and the chamber configuration. Theoretically, it is possible to estimate these values; however, it is very dif
17、ficult and tedious to accurately predict them. They are normally determined through initial hot-fire tests, which was also one of the objectives of the fourth test. For this particular test, the test duration was set for 2.00 seconds and the incident occurred at 1.38 seconds within the duration. Giv
18、en the lack of data, this duration should be set conservatively at a lower value. If the duration does not allow enough time for ignition, a small incremental step can be added to the waiting time. This method, however, may require more tests in order to study the startup conditions.Provided by IHSN
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS13102002LESSONSLEARNEDNASAMSFCARMYVORTEXCHAMBERTESTINCIDENTPDF

链接地址:http://www.mydoc123.com/p-1018949.html