REG NASA-LLIS-1216-1999 Lessons Learned Use of Pathfinder Strategy to identify configuration process anomalies.pdf
《REG NASA-LLIS-1216-1999 Lessons Learned Use of Pathfinder Strategy to identify configuration process anomalies.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1216-1999 Lessons Learned Use of Pathfinder Strategy to identify configuration process anomalies.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1216Lesson Info:a71 Lesson Number: 1216a71 Lesson Date: 1999-04-21a71 Submitting Organization: JSCa71 Submitted by: Roger Striegel/ Ronald A. MontagueSubject: Use of “Pathfinder“ Strategy to identify configuration process anomalies Description of Driving Event: The initial run
2、s of an On-Orbit Constraint Test (OOCT) at KSC ran into a number of anomalies. These initial runs were the first attempts (or “pathfinder“ event) in a series of OOCT from which lessons learned would result in smoother, more efficient OOCTs prior to future flights. The OOCT are a series of tests that
3、 emulate one side of an element to element interface using test aids. These Test Aids are set up in a test configuration with the flight element to be tested. The flight crew actually comes to KSC to conduct the test on the flight hardware. The OOCT is considered training for the crew as well as a c
4、heckout of the on-orbit procedure with the actual flight hardware.Both Extra-vehicular Activities (EVA) and the Inter-vehicular Activities (IVA) are subject to the OOCT discipline. In an OOCT, connect cables, fluid ducts and umbilicals on the flight are run in a test configuration so that routing, m
5、ating/de-mating of the flight hardware, clocking, length of lines, stress/strain or twisting of cables and potential obstructions to be encountered can be evaluated.This pathfinder OOCT occurred for Flight 3A where Node 1 was emulated (Node 1 is on-orbit) and with PMA3 (Flight 3A) which had been del
6、ivered (DD250) to NASA. The PMA3 configuration actually encountered during the test set-up was different than envisioned from review of the drawing package from which the test aid alignment data and test procedure had been generated. The test procedures are generated from the on-orbit operational se
7、quences being built by mission planners (in this case, in JSCs Missions Operations Directorate, or MOD).Because of the misunderstandings documented in the root causes below, the test alignments, setup of the test aids and the actual conduct of the tests exceeded the planned test timeline. While the
8、test was completed successfully, a regression test will have to be conducted to repeat parts of the test because of insufficient / incorrect data available for the test procedure.Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Root causes: 1. Setup a
9、nd Alignment Data for the Test Aid was insufficient, incorrect and misunderstood by the KSC support teams responsible for the test aid setup and alignment of the test configuration. There was no tabletop review of this data with KSC prior to these pre-test activities nor was the data formally releas
10、ed prior to pretest activities.2. The On-Orbit Constraints Meeting was not utilized as a requirements gate review. Since this was the initial test, this meeting was process oriented and lacked specific implementation requirements to be agreed to and baselined.3. Hardware fit interference - overhangi
11、ng of PMA3 by EVA test aid - was not anticipated. It was a surprise to the test team. With appropriate configuration control processes, this would not have occurred. Scaffolding and protective padding was applied to the element.4. Undocumented mating targets were applied to mating / sealing surfaces
12、 because target locations identified were not on same planar surface as expected. Because the test technicians had done similar exercises before, the targets were applied successfully prior to test.5. N2 and O2 lines were incorrectly called out in the test procedure. Test Procedure was written to th
13、e PMA3 to Node3 ICD that is the correct data source. This was questioned prior to TRR and PMA3 Flight Element team provides a sketch of the lines which was also incorrect. The running of the test identified several errors including this one.Lesson(s) Learned: When faced with first-time performance o
14、f complex tests and operations, consider using “pathfinder“ disciplines to perform process shakedowns to identify loopholes and escapes.Recommendation(s): 1. Test Aid Configuration Control2. a) Identify a KSC Test Conductor with knowledge of the flight hardware. b) Conduct tabletop reviews of all te
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS12161999LESSONSLEARNEDUSEOFPATHFINDERSTRATEGYTOIDENTIFYCONFIGURATIONPROCESSANOMALIESPDF

链接地址:http://www.mydoc123.com/p-1018855.html