REG NASA-LLIS-1184--1991 Lessons Learned - Orbiter Fuel Cell Power Down Mishap Investigation Board Report of August 12 1991.pdf
《REG NASA-LLIS-1184--1991 Lessons Learned - Orbiter Fuel Cell Power Down Mishap Investigation Board Report of August 12 1991.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1184--1991 Lessons Learned - Orbiter Fuel Cell Power Down Mishap Investigation Board Report of August 12 1991.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1184Lesson Info:a71 Lesson Number: 1184a71 Lesson Date: 1991-08-12a71 Submitting Organization: KSCa71 Submitted by: Jackie E. Smith/Eric RaynorSubject: Orbiter Fuel Cell Power Down Mishap Investigation Board Report of August 12, 1991 Description of Driving Event: On August 12,
2、 1991, starting at approximately 3:58 a.m. EDT, two of the three fuel cells installed on Orbiter Atlantis, OV104, were possibly damaged when inadvertently left connected to the orbiter main busses for 16 hours and 36 minutes without water removal capability. The accumulation of water has the potenti
3、al for severe damage to the fuel cells. Atlantis landed at the Kennedy Space Center (KSC) on August 11, 1991, at 8:24 a.m. EDT after completing the STS-43 mission. The vehicle was undergoing deservice and safing operations in the Orbiter Processing Facility (OPF) High Bay 2 as part of the turnaround
4、 activities for its next mission, STS-44. The work effort was being accomplished by a NASA contractor.The mishap occurred when helium was inadvertently ingested into the fuel cell oxygen (02) supply causing a sudden performance loss by Fuel Cells 2 and 3 resulting in the loss of power to orbiter bus
5、ses B and C. This necessitated the implementation of the Emergency Power Down Procedure. The Emergency Power Down Procedure consisted of 6 crew module switch actions and was intended to electrically isolate the fuel cells from the orbiter main busses. The Emergency Power Down Procedure did not addre
6、ss the loss of multiple fuel cells with no vehicle ground power and, therefore, did not accomplish the required isolation of Fuel Cells 2 and 3 from the orbiter main busses. Emergency power down procedures have been used many times during shuttle processing, most often due to loss of orbiter cooling
7、. The Emergency Power Down Procedure did not include the provision that the only functioning bus should be the last commanded off. Since it did not address this, there was no power available to drive the Fuel Cell 2 and 3 to main bus motor switches to the open (isolate) position.During first shift a
8、nd early second shift on August 12, 1991, there were reports of occasional alarms and noises, such as fans operating, emanating from the “powered down“ orbiter. These reports, at first discounted, were investigated and determined to be resulting from the power generation of Fuel Provided by IHSNot f
9、or ResaleNo reproduction or networking permitted without license from IHS-,-,-Cells 2 and 3 which were still connected to the Orbiter Main Bus B and Main Bus C respectively. The fuel cells were removed from the busses at approximately 8:34 p.m. EDT August 12, 1991 by use of ground power through the
10、Orbiter ground umbilicals.Lesson(s) Learned: The chemical reaction within a fuel cell continues to generate electrical power and water when reactants (02 and H2) are present and electrical loads connected. In this case the Fuel Cells 2 and 3, with electrical loads connected, were at reduced voltage
11、levels because helium had mixed with the 02 in quantities sufficient to reduce the efficiency of the fuel cells.The helium ingestion was a result of an inadequate test procedure that performed ground support equipment (GSE) setups for controlled venting, fuel cell power down, cryogenic drain. This p
12、rocedure had been reviewed and approved by the appropriate engineering organizations. STS-43 was the third KSC landing since the Challenger accident and the first time the GSE back pressure regulator confidence test was performed while the fuel cells were powered. The pressure specified in the test
13、procedure for the GSE back pressure regulator exceeded the vehicle 02 manifold pressure allowing GSE helium to enter the fuel cell 02 supply. The power reactanta storage and distribution fuel cell (PRSD/FC) Engineer thought the GSE pressure could be controlled by additional valve cycling not covered
14、 in the procedure and elected to perform the back pressure regulator test instead of implementing a real time change to the test procedure. The GSE pressure exceeded the orbiter onboard flight disconnect specification cracking pressure by 12 psi and 6 psi for five seconds and eight seconds respectiv
15、ely. GSE pressure levels commanded by the PRSD/FC engineer were within limits defined in the test procedure.Ingestion of helium into the fuel cells does not harm them, although it does degrade performance. This performance loss initiated a sequence of events which led to potential damage to Fuel Cel
16、ls 2 and 3.The Shuttle emergency power down procedures must react to all possible contingencies and configure the hardware to an absolute safe condition. The test teams reaction to unplanned events must be preplanned and implemented without hesitation or deliberation. A fuel cell is considered the m
17、ost reliable power source available and therefore multiple failures were not considered to be a realistic occurrence. Engineering and management, both government and contractor, had developed a feeling of security regarding emergency power down. The Emergency Power.Down procedure was developed in 19
18、79 for the STS-1 mission, reviewed as part of the post-Challenger Return-to-Flight activities, and has remained essentially unchanged. In retrospect, the technical community should have recognized that these were unusual circumstances, ie., loss of 2 fuel cells, no ground power, etc., and evaluated
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS11841991LESSONSLEARNEDORBITERFUELCELLPOWERDOWNMISHAPINVESTIGATIONBOARDREPORTOFAUGUST121991PDF

链接地址:http://www.mydoc123.com/p-1018823.html