REG NASA-LLIS-1183--1989 Lessons Learned - Orbiter Processing Facility Bay 2 Water Deluge System Flow Mishap Investigation Board Report of October 25 1989.pdf
《REG NASA-LLIS-1183--1989 Lessons Learned - Orbiter Processing Facility Bay 2 Water Deluge System Flow Mishap Investigation Board Report of October 25 1989.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1183--1989 Lessons Learned - Orbiter Processing Facility Bay 2 Water Deluge System Flow Mishap Investigation Board Report of October 25 1989.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1183Lesson Info:a71 Lesson Number: 1183a71 Lesson Date: 1989-10-25a71 Submitting Organization: KSCa71 Submitted by: Thomas Utsman/ Eric RaynorSubject: Orbiter Processing Facility Bay 2 Water Deluge System Flow Mishap Investigation Board Report of October 25, 1989 Description o
2、f Driving Event: The Orbiter Processing Facility (OPF) Bay 2 Firex Deluge Zone 3 Viking arm valve AV1.3-2 was leaking, and on September 21, 1989, Problem Report (PR) number PV-6-140247 was initiated to replace defective parts. During system leak check operations following valve repair, water flow fr
3、om zone 3 (directly over the Orbiter) occurred in OPF Bay 2. The time of first flow was established as 10:28 AM on September 24, 1989, as recorded by OPF Water Pump House instrumentation due to diesel pump startup. The Zone 3 water flow over the Orbiter was at a reduced rate, with only a partial noz
4、zle discharge pattern.Shuttle Processing Contract (SPC) Water Systems technicians were cycling the manual arming and firing valves while leak checking the system. Only a few minutes had passed from the time they cracked open (2 turns) the system manual supply valve until they heard about the water f
5、low problem in Bay 2. The SPC Lead Water Systems technician ran into the OPF to see what was wrong and noted the deluge flow. He returned to the manual activation station behind the OPF and found that two SPC ground support equipment (GSE) technicians had opened the manual arming and firing valve to
6、 Zones 1, 2, 3, 4, and 5. (It is presumed Zone 3 did not flow additional water and had been deactivated by this time.) The Lead Water Systems technician then closed all the open manual arming and firing valves, as well as the manual supply isolation valves to stop all Bay 2 water flow.The scenario t
7、hat lead to the two GSE technicians being at the deluge system manual flow control valve station is as follows:After the flow from Zone 3 occurred, the SPC OPF Bay 1 Site Division Manager asked a GSE technician to find someone who could turn the system off. This GSE technician, accompanied by a co-w
8、orker, proceeded to the manual activation station behind Bay 2. Upon arrival, they proceeded to Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-position the manual arming and firing valves to Zones 1, 2, 3, 4, and 5 to the “on“ position, thinking the
9、y were turning the firex system off. This turned on deluge system Zones 1, 2, 4, and 5 (Zone 3 had already been deactivated) to the “full on“ mode. The Lead Water Systems technician then returned to the manual valve panels, proceeded to turn the manual arming and firing valves to the “off“ position,
10、 and then helped his technicians close the manual supply isolation valves to Zones 1 through 5, which stopped all water flow.Lesson(s) Learned: The primary cause of the mishap was failure to follow the procedural instructions in PR number PV-6-140247, in which: (1) facility water technicians added a
11、 flow test on the Zone 3 system after valve diaphragm repair, and (2) in not fully closing or in improperly reopening the manual riser isolation valve, water was allowed to flow into Zone 3 of the OPF Bay 2 water deluge system.Contributing causes included the following:1. The OPF GSE technicians, wh
12、o are members of the “Contingency Team,“ had not been adequately trained in the operation of the OPF water deluge system. This led to the OPF GSE “Contingency Team“ technicians activating Zones 1, 2, 3, 4, and 5 of the Bay 2 deluge system, while thinking they were turning the system off.2. A thoroug
13、h pre-task briefing (PTB) was not held for the water deluge system valve repair task, which could have prevented deviation from the repair procedure by the facility water technicians.3. The labeling on the remote manual arming and firing valve activation station of the OPF water deluge system was mi
14、sinterpreted. This contributed to the OPF GSE technicians activating Zones 1, 2, 3, 4, and 5 of the Bay 2 deluge system when they believed they were turning the system off.4. The remote manual arming and firing valves are in the “on“ position when perpendicular to the water lines, which is not the i
15、ndustry norm for hydraulic systems. This contributed to the OPF GSE technicians believing they were closing the valves by positioning them perpendicular to the water line when, in fact, they were opening the valves. This human factor problem was not addressed in the System Assurance Analysis for the
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS11831989LESSONSLEARNEDORBITERPROCESSINGFACILITYBAY2WATERDELUGESYSTEMFLOWMISHAPINVESTIGATIONBOARDREPORTOFOCTOBER251989PDF

链接地址:http://www.mydoc123.com/p-1018822.html