REG NASA-LLIS-1033-2001 Lessons Learned Controlling Risk on Cost-Capped Schedule-Driven Technology Validation Projects (1998).pdf
《REG NASA-LLIS-1033-2001 Lessons Learned Controlling Risk on Cost-Capped Schedule-Driven Technology Validation Projects (1998).pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1033-2001 Lessons Learned Controlling Risk on Cost-Capped Schedule-Driven Technology Validation Projects (1998).pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1033Lesson Info:a71 Lesson Number: 1033a71 Lesson Date: 2001-01-01a71 Submitting Organization: JPLa71 Submitted by: David H. LehmanSubject: Controlling Risk on Cost-Capped, Schedule-Driven, Technology Validation Projects (1998) Abstract: Deep Space 1 (DS1) was a cost-capped, s
2、chedule-driven, technology validation project, designed to flight validate 12 advanced technologies that represented major breakthroughs over state-of-the-art systems. DS1 exceeded its mission success criteria, both in terms of technology demonstration and mission duration.The lesson lists 7 recomme
3、ndations/success criteria for high risk, cost capped missions.Description of Driving Event: Deep Space 1 (DS1) was a cost-capped, schedule-driven, technology validation project, designed to flight validate 12 advanced technologies that represented major breakthroughs over state-of-the-art systems. A
4、n aerospace industry partner was originally selected to provide much of the spacecraft hardware and integration, but ultimately required significant JPL expertise and assistance. JPL was originally responsible for project management and several other elements, but assumed significant additional resp
5、onsibilities. NASA Lewis (now Glenn) Research Center, through the NSTAR program provided the highest priority technology, the ion propulsion system.DS1 exceeded its mission success criteria, both in terms of technology demonstration and mission duration. In addition, it provided the first close-up s
6、pectacular views of a cometary nucleus as part of a very successful extended mission.Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-refer to D descriptionDFrom the very beginning, the project accepted very high risk in developing and flying the miss
7、ion. The accepted risk was compounded by what turned out to be insufficient schedule and funding, leading to insufficient review and oversight of several crucial processes:a71 A lack of an early and complete review of the project to (1) assess adequacy of plans, schedule, cost, resource margins, and
8、 (2) gain a full understanding of the projects risk posture.a71 Cost and schedule reserves that were inadequate given the many advanced technologies to be demonstrated during the mission.a71 Level 1 requirements and mission success criteria that remained unresolved until very late in development.a71
9、 Accepting a formulation phase that was too short for the team to develop a good plan for implementation.a71 A funding profile that lagged the fast-paced schedule, and caused serious inefficiencies during project start-up. This delayed early and full integration of the industrial partner into the pr
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS10332001LESSONSLEARNEDCONTROLLINGRISKONCOSTCAPPEDSCHEDULEDRIVENTECHNOLOGYVALIDATIONPROJECTS1998PDF

链接地址:http://www.mydoc123.com/p-1018678.html