1、Lessons Learned Entry: 0747Lesson Info:a71 Lesson Number: 0747a71 Lesson Date: 2000-02-28a71 Submitting Organization: GRCa71 Submitted by: Joe MorrisSubject: Facilities, Costing Of Contracts Description of Driving Event: The construction cost estimate for the project was equivalent to the project au
2、thority and as a result some work that was suspect of needing to be replaced was not included in the bid documents. The actual scenario was that electrical lighting was in the documents to be replaced in a Mod and Rehab project, however, the existing conduit and wire was planned to be reused.After t
3、he project was competitively bid, the actual contract price was less than the project authority. If the electrical work had been included as an option to the contract the cost would have be a more competitive price. The electrical work was not included in an option and as a result the change order t
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS07472000LESSONSLEARNEDFACILITIESCOSTINGOFCONTRACTSPDF

链接地址:http://www.mydoc123.com/p-1018393.html