1、*USACE / NAVFAC / AFCESA / NASA UFGS-08 51 13 (May 2011)-Preparing Activity: NAVFAC SupersedingUFGS-08 51 13 (August 2009)UFGS-08 51 13 (January 2008) UFGS-08 51 13.00 20 (July 2006)UFGS-08 51 13.00 40 (October 2006)UFGS-08 51 14.00 10 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences ar
2、e in agreement with UMRL dated April 2011*SECTION TABLE OF CONTENTSDIVISION 08 - OPENINGSSECTION 08 51 13ALUMINUM WINDOWS05/11PART 1 GENERAL1.1 REFERENCES1.2 CERTIFICATION1.3 SUBMITTALS1.4 QUALITY ASSURANCE1.4.1 Shop Drawing Requirements1.4.2 Sample Requirements1.4.2.1 Finish Sample Requirements1.4.
3、2.2 Window Sample Requirements1.4.3 Design Data Requirements1.4.4 Test Report Requirements1.5 DELIVERY AND STORAGE1.6 PROTECTION1.7 SUSTAINABLE DESIGN REQUIREMENTS1.7.1 Local/Regional Materials1.7.2 Environmental Data1.7.3 Plastic Identification1.8 FIELD MEASUREMENTS1.9 PERFORMANCE REQUIREMENTS1.9.1
4、 Wind Loading Design Pressure1.9.2 Tests1.10 DRAWINGS1.11 WINDOW PERFORMANCE1.11.1 Structural Performance1.11.2 Minimum Antiterrorism Performance1.11.2.1 Computational Design Analysis Method1.11.2.2 Alternate Dynamic Design Analysis Method1.11.2.3 Standard Airblast Test Method1.11.3 Air Infiltration
5、1.11.4 Water Penetration1.11.5 Thermal PerformanceSECTION 08 51 13 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.11.6 Life Safety Criteria1.11.7 Sound Attenuation1.12 QUALIFICATION1.13 MOCK-UPS1.14 WARRANTYPART 2 PRODUCTS2.1 WINDOWS2.1.1 Aw
6、ning Windows (AP)2.1.2 Casement Windows (C)2.1.3 Hung Windows (H)2.1.3.1 Window Materials2.1.4 Horizontal Sliding Windows (HS)2.1.5 Projected Windows (AP)2.1.6 Top-Hinged Windows (TH)2.1.7 Vertically Pivoted Windows (VP)2.1.8 Fixed Windows (F)2.1.9 Forced Entry Resistant Windows2.1.10 Glass and Glaz
7、ing2.1.11 Calking and Sealing2.1.12 Weatherstripping2.1.13 Sash Poles2.2 FABRICATION2.2.1 Provisions for Glazing2.2.2 Weatherstripping2.2.3 Fasteners2.2.4 Adhesives2.2.5 Drips and Weep Holes2.2.6 Combination Windows2.2.7 Mullions and Transom Bars2.2.8 Accessories2.2.8.1 Hardware2.2.8.2 Fasteners2.2.
8、8.3 Window-Cleaner Anchors2.2.8.4 Window Anchors2.2.9 Finishes2.2.9.1 Anodic Coating2.2.9.2 Organic Coating2.2.10 Screens2.3 SPECIAL OPERATORS2.3.1 Pole Operators2.3.2 Extension Crank Operators2.3.3 Mechanical Operators2.4 THERMAL-BARRIER WINDOWS2.5 MULLIONS2.6 WINDOW CLEANERS BOLTSPART 3 EXECUTION3
9、.1 SCHEDULE3.2 INSTALLATION3.2.1 Method of Installation3.2.2 Dissimilar Materials3.2.3 Anchors and Fastenings3.2.4 Adjustments After Installation3.3 CLEANING3.4 WASTE MANAGEMENTSECTION 08 51 13 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,- E
10、nd of Section Table of Contents -SECTION 08 51 13 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-08 51 13 (May 2011)-Preparing Activity: NAVFAC SupersedingUFGS-08 51 13 (August 2009)UFGS-08 51 13 (January 2
11、008) UFGS-08 51 13.00 20 (July 2006)UFGS-08 51 13.00 40 (October 2006)UFGS-08 51 14.00 10 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2011*SECTION 08 51 13ALUMINUM WINDOWS05/11*NOTE: This guide specification covers the requirements for R, LC,
12、CW and AW performance class aluminum windows.Note: Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, d
13、eleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments, suggestions and recommended changes for this guide specification are welc
14、ome and should be submitted as a Criteria Change Request (CCR).*1. Windows requiring UL fire rating must be steel, and may occur in conjunction with aluminum windows which cannot be approved for this use. When steel windows are used in conjunction with aluminum, specify finish matching aluminum wind
15、ows. Steel windows should be specified in Section 08 51 23 STEEL WINDOWS.2. Aluminum windows are not acceptable for use as security windows which should be steel, specified in Section 08 51 23 STEEL WINDOWS. Security steel windows are designed and constructed to give protection against unauthorized
16、entrance and removal SECTION 08 51 13 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-of materials from warehouses and other storage type areas; they are not designed for detention use. Guard windows for detention use are not included in this g
17、uide; where such windows are desired, consult Steel Window Institute Recommended Specifications and manufacturers data, and specify in Section 08 51 23 STEEL WINDOWS.3. Specify the following items of related work under other sections of the specifications:a. Glass and glazing and the furnishing of g
18、lazing clips and gaskets.b. Calking and sealants.c. Structural building supports at window mullions.d. Wood subframes for windows in frame walls.e. Drilling and tapping for attachment of window shades, drapery rods, and venetian blinds. The drilling and tapping of window frames to receive brackets f
19、or shades, venetian blinds, and curtain rods has been omitted from this specification. It is contemplated that this work will be done after erection of windows by the trade for the item to be installed. On projects where factory drilling for these items is required, revise this specification accordi
20、ngly.f. Brackets and supports for window shades, drapery rods, and venetian blinds.g. Electrical requirements for motor driven operators.*NOTE: On the drawings, show:1. Sizes and types of windows; metal and wood subframes, casings, or stools; and hardware.2. Sizes, location, and swing of ventilators
21、; direction of slide for sliding ventilators; location and details of fixed sash.3. Typical window sections and details. Show glass thickness. Show special glazing.4. Method of anchoring windows to adjoining construction; size and types of clips, anchors, screws, or other fasteners.5. Details of non
22、structural mullions and mullion covers; details of anchoring and reinforcing nonstructural mullions at windows to receive window cleaner anchors.SECTION 08 51 13 Page 5Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-6. Number and locations of window
23、cleaner anchors.7. Locations of windows requiring special operators. Show method of operation and concealment of operators, cables and rods. Show wiring diagram for motor driven operators.8. Locations of windows designated as forced entry resistant.*PART 1 GENERAL1.1 REFERENCES*NOTE: Issue (date) of
24、 references included in project specifications need not be more current than provided by the latest guide specification. Use of SpecsIntact automated reference checking is recommended for projects based on older guide specifications.*The publications listed below form a part of this specification to
25、 the extent referenced. The publications are referred to within the text by the basic designation only.ALUMINUM ASSOCIATION (AA)AA DAF-45 (2003; Reaffirmed 2009) Designation System for Aluminum FinishesAMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)AAMA 1302.5 (1976) Voluntary Specifications
26、 for Forced-Entry Resistant Aluminum Prime WindowsAAMA 1503 (2009) Voluntary Test Method for Thermal Transmittance and Condensation Resistance of Windows, Doors and Glazed Wall SectionsAAMA 2603 (2002) Voluntary Specification, Performance Requirements and Test Procedures for Pigmented Organic Coatin
27、gs on Aluminum Extrusions and PanelsAAMA 2604 (2005) Voluntary Specification, Performance Requirements and Test Procedures for High Performance Organic Coatings on Aluminum Extrusions and PanelsAAMA 2605 (2005) Voluntary Specification, Performance Requirements and Test Procedures for Superior Perfor
28、ming Organic Coatings on Aluminum Extrusions and PanelsSECTION 08 51 13 Page 6Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-AAMA 611 (1998; R 2004) Voluntary Specification for Anodized Architectural AluminumAAMA 701/702 (2004) Voluntary Specificati
29、on for Pile Weatherstripping and Replaceable Fenestration WeathersealsAAMA 902 (1992; R 1999; R 2007) Voluntary Specification for Sash BalancesAAMA WSG.1 (1995) Window Selection GuideAAMA/WDMA/CSA 101/I.S.2/A440 (2008; Update 1 2008; Update 2 2008; Update 3 2009) North American Fenestration Standard
30、/Specification for Windows, Doors, and SkylightsASTM INTERNATIONAL (ASTM)ASTM A276 (2010) Standard Specification for Stainless Steel Bars and ShapesASTM D 1972 (1997; R 2005) Standard Practice for Generic Marking of Plastic ProductsASTM E 1300 (2009a) Determining Load Resistance of Glass in Building
31、sASTM E 2129 (2005) Standard Practice for Data Collection for Sustainability Assessment of Building ProductsASTM F 1642 (2004; R 2010) Standard Test Method for Glazing and Glazing Systems Subject to Airblast LoadingsASTM F 2248 (2009) Standard Practice for Specifying an Equivalent 3-Second Duration
32、Design Loading for Blast Resistant Glazing Fabricated with Laminated GlassGREEN SEAL (GS)GS-36 (2000) Commercial AdhesivesINTERNATIONAL WINDOW CLEANING ASSOCIATION (IWCA)IWCA I-14.1 (2001) Window Cleaning Safety StandardNATIONAL FENESTRATION RATING COUNCIL (NFRC)NFRC 100 (2010) Procedure for Determi
33、ning Fenestration Product U-FactorsNFRC 200 (2010) Procedure for Determining Fenestration Product Solar Heat Gain Coefficient and Visible Transmittance at Normal IncidenceSECTION 08 51 13 Page 7Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-NATIONAL
34、 FIRE PROTECTION ASSOCIATION (NFPA)NFPA 101 (2009; TIA 09-1; TIA 09-2) Life Safety CodeSOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)SCAQMD Rule 1168 (1989; R 2005) Adhesive and Sealant ApplicationsU.S. GREEN BUILDING COUNCIL (USGBC)LEED (2002; R 2005) Leadership in Energy and Environmental De
35、sign(tm) Green Building Rating System for New Construction (LEED-NC)1.2 CERTIFICATIONEach prime window unit must bear the AAMA Label warranting that the product complies with AAMA/WDMA/CSA 101/I.S.2/A440. Certified test reports attesting that the prime window units meet the requirements of AAMA/WDMA
36、/CSA 101/I.S.2/A440, including test size, will be acceptable in lieu of product labeling.1.3 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. Submittals should
37、be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through the Con
38、tractors Quality Control system. Only add a “G” if the submittal is sufficiently important or complex in context of the project.For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the “G“ designation to indic
39、ate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: “AE“ for Architect-Engineer; “DO“ for District Office (Engineering Division or other organization in the District Office); “AO“ for Area Office; “RO“ for Resident Office; and “PO“ for Project Office.
40、 Codes following the “G“ typically are not used for Navy projects.Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.*SECTION 08 51 13 Page 8Provided by IHSNot for ResaleNo reproduction or networking permitted without license
41、from IHS-,-,-Government approval is required for submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval.for information only. When used, a designation following the “G“ designation identifies the office that will review the submittal fo
42、r the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-02 Shop DrawingsWindows; GFabrication DrawingsSD-03 Product DataWindows; GHardware; GFasteners; G; (LEED)Window performance; GThermal-Barrier Windows; GMullions; GWindow Cleaners Bolts; GSubmit documen
43、tation indicating percentage of post-industrial and post-consumer recycled content per unit of product. Indicate relative dollar value of recycled content products to total dollar value of products included in project.Screens; GWeatherstripping; GAccessories; G Adhesives; (LEED)Submit manufacturers
44、product data, indicating VOC content.Thermal performanceSubmit documentation for Energy Star qualifications. Local/Regional Materials; (LEED)Documentation indicating distance between manufacturing facility and the project site. Indicate distance of raw material origin from the project site. Indicate
45、 relative dollar value of local/regional materials to total dollar value of products included in project. Environmental DataSECTION 08 51 13 Page 9Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-SD-04 SamplesFinish SampleWindow SampleSD-05 Design DataStructural calculatio