1、*USACE / NAVFAC / AFCESA / NASA UFGS-02 01 50 (May 2010)-Preparing Activity: USACE SupersedingUFGS-02 01 50 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION TABLE OF CONTENTSDIVISION 02 - EXISTING CONDITIONSSECTION 02 01 50OPERATION, M
2、AINTENANCE, AND PROCESS MONITORING FOR SOIL VAPOR EXTRACTION(SVE) SYSTEMS05/10PART 1 GENERAL1.1 MEASUREMENT AND PAYMENT1.1.1 Unit Pricing1.1.2 Training1.1.3 Disposal and Replacement of Vapor Phase Activated Carbon1.1.4 Pneumatic Flow Meter Testing1.1.5 Completion Testing1.2 REFERENCES1.3 PROJECT DES
3、CRIPTION1.3.1 Chemical Testing1.3.2 Assistance in Preparing O these costs are typically covered by Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL. Unit pricing should also be considered for replacement of granular activated carbon (GAC), if GAC vapor stream treatment will be required.These par
4、agraphs should be coordinated with Sections 43 13 13.13 VAPOR PHASE ACTIVATED CARBON ADSORPTION UNITS, 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL, and 43 11 00 FANS/BLOWERS/PUMPS; OFF-GAS.The bid sheet should include separate, optional items for tasks such as: training, pneumatic flow meter testin
5、g, and completion testing.*Measurement shall be based on completion of contract requirements. Payment will be at the respective contract prices in the bidding schedule.SECTION 02 01 50 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.1.1 Unit
6、Pricing*NOTE: Incentives for the Contractor to complete remedial action in a timely manner should be incorporated into the pricing structure, if possible. Unit pricing alternatives for payment include: hours of operation, volume of air extracted, and mass of contaminants removed.Although pricing by
7、mass of contaminants removed creates incentive, mass of contaminants removed is more difficult to accurately measure than time or air volumes. Also there is typically a high degree of uncertainty in predicting mass removal rates, which will make it difficult for bidders to assign reasonable prices w
8、hen preparing bids.Another performance based payment option is to make periodic payments to the Contractor based on the degree of reduction in contaminant levels. For example, partial payment to the Contractor is made based on the percentage reduction in contaminant levels. However this type of paym
9、ent scheme should be used with caution, since removal rates typically decrease as contaminant levels decrease; e.g., it may take 3 times as long to go from 25 to 10 mg/kg as it takes to go from 100 to 25 mg/kg.Lump sum pricing, with performance requirements (see paragraph Operation of the SVE System
10、), is generally recommended for Operations, Maintenance and Process Monitoring. Under this pricing structure, the Contractor receives periodic payments (e.g., monthly) so long as performance requirements are being met. If performance requirements are not met, then the Contracting Officer may withhol
11、d payment until the Contractor demonstrates that performance requirements are being met.If it is expected that large volumes of condensate will be generated, and that treatment or offsite disposal will be required; then a separate paragraph should be added to cover treatment and disposal of condensa
12、te. A unit pricing structure would be appropriate to pay for treatment or offsite disposal of condensate.*Compensation shall be a lump sum price for Operation of the SVE System, Maintenance, and Process Monitoring. Costs for Contaminated Material Storage and Disposal shall also be included in this p
13、rice. Costs for replacement adsorption media for the vapor stream treatment system is covered under a separate paragraph and is not included in this price. Physical and chemical testing performed in the field, and sampling shall be included in this price. Costs for laboratory analysis of samples is
14、covered in Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL and is not included in this price.SECTION 02 01 50 Page 5Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.1.2 Training*NOTE: If it is expected that close out of the site will be complet
15、ed within the period of the contract, then Training should be listed as an optional item on the bid sheet.*Compensation shall be a lump sum price for Training.1.1.3 Disposal and Replacement of Vapor Phase Activated Carbon*NOTE: This paragraph should be deleted if any of the following conditions appl
16、y: vapor steam treatment will not be required; the vapor stream treatment system does not use activated carbon; or payment for activated carbon is covered under a separate Section. *Compensation for disposal of spent vapor phase activated carbon shall be by the contract unit price schedule for each
17、_ kg pound, based on the dry weight of the spent activated carbon _. Compensation for replacement of spent vapor phase activated carbon shall be by the contract unit price schedule for each _kg pound, based on invoices from the supplier of the replacement activated carbon _.1.1.4 Pneumatic Flow Mete
18、r Testing*NOTE: This paragraph should be deleted if pneumatic flow meter testing will not be required. If this paragraph is retained, the bid sheet should include a separate, optional item for pneumatic flow meter testing.*Compensation for pneumatic flow meter testing shall be by the contract unit p
19、rice schedule on a per well basis. Physical and chemical testing performed in the field, and sampling shall be included in this price. Costs for laboratory analysis of samples is covered in Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL, and is not included in this price.1.1.5 Completion Testi
20、ng*NOTE: Completion testing is defined as testing that is performed determine if regulatory requirements have been met, so that the SVE system can be permanently shut down.This paragraph should be deleted if completion testing will not be included in the contract. If this paragraph is retained, the
21、bid sheet should include a separate, optional item for completion testing.SECTION 02 01 50 Page 6Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*Compensation shall be a lump sum price for Completion Testing. Physical and chemical testing performed i
22、n the field, and sampling shall be included in this price. Costs for laboratory analysis of samples is covered in Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL, and is not included in this price.1.2 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guid
23、e specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.Use the Reference Wizards Check Reference feature when you add a RID outside of the Sections Reference Article to automatically place the
24、 reference in the Reference Article. Also use the Reference Wizards Check Reference feature to update the issue dates.References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.*The
25、 publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.ASTM INTERNATIONAL (ASTM)ASTM D 4750 (1987; R 2001) Determining Subsurface Liquid Levels in a Borehole or Monitoring Well (Observation
26、 Well)U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)40 CFR 302 Designation, Reportable Quantities, and Notification1.3 PROJECT DESCRIPTION1.3.1 Chemical TestingChemical sampling and analysis required in this section shall be conducted in accordance with SECTION 01 35 45.00 10 CHEMICAL DATA
27、 QUALITY CONTROL.1.3.2 Assistance in Preparing O 24 hours worth of demonstrating operation, maintenance, and monitoring protocols during facility tours; and 4 hours worth of answering follow-up questions _.1.3.3 Sequencing and Scheduling*NOTE: The initial period of operation should not begin until t
28、he Contractor has fulfilled the requirements for commissioning and demonstration of the full-scale SVE system.*The first period of operation of the full-scale system shall not be initiated until after test and inspection reports in Section 02 62 16 COMMISSIONING AND DEMONSTRATION FOR SOIL VAPOR EXTR
29、ACTION (SVE) SYSTEMS have been submitted and approved. Notify the Contracting Officer not less than 14 _ calendar days prior to initiating the first period of operation.1.4 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following
30、list to reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an exist
31、ing “G” if the submittal item is not SECTION 02 01 50 Page 8Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-complex and can be reviewed through the Contractors Quality Control system. Only add a “G” if the submittal is sufficiently important or compl
32、ex in context of the project.For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the “G“ designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are
33、: “AE“ for Architect-Engineer; “DO“ for District Office (Engineering Division or other organization in the District Office); “AO“ for Area Office; “RO“ for Resident Office; and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy, Air Force, and NASA projects.Choose the f
34、irst bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.Specific testing procedures should be addressed in the Sampling and Analysis Plan required by Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL.*Government approval is required for sub
35、mittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval. information only. When used, a designation following the “G“ designation identifies the office that will review the submittal for the Government. Submit the following in accordance wi
36、th Section 01 33 00 SUBMITTAL PROCEDURES:SD-03 Product DataOperation of the SVE System; G; G, _, _Maintenance; G; G, _Process Monitoring; G; G, _Contaminated Material Storage and Disposal; G; G, _Completion Testing; G; G, _SD-06 Test ReportsLaboratory Analysis Reports; G; G, _Completion Testing Repo
37、rt; G; G, _SD-07 CertificatesOperator Qualifications; G; G, _SD-10 Operation and Maintenance DataOperations Reports; G; G, _Operations Log; G; G, _Maintenance Log; G; G, _Contract Completion Report; G; G, _SECTION 02 01 50 Page 9Provided by IHSNot for ResaleNo reproduction or networking permitted wi
38、thout license from IHS-,-,-1.5 QUALITY ASSURANCE 1.5.1 Permits and Licenses*NOTE: It is important for the designer to become familiar with the appropriate state and local requirements to determine if there is a need to obtain an operating permit for the system and to include those requirements in th
39、ese paragraphs. The designer should also bear in mind that any SVE system operated as part of site remediation under CERCLA authority does not require federal, state or local permits. This includes all NPL and non-NPL sites being remediated under CERCLA authority such as DERP, IRP, FUDS, or BRAC pro
40、gram projects. Permits that have already been acquired should be attached to the specifications and referenced.These paragraphs should be coordinated with Sections 01 57 20.00 10 ENVIRONMENTAL PROTECTION and 43 13 13.13 VAPOR PHASE ACTIVATED CARBON ADSORPTION UNITS (if used).*Obtain required federal
41、, state, and local permits for operation of the SVE system.1.5.2 Air Emissions*NOTE: An air pathway analysis should be performed during design to determine if air monitoring will be required. Guidance on air pathway analyses is provided in EP 1110-1-21 - Air Pathway Analysis for the Design of Hazard
42、ous, Toxic, and Radioactive Waste (HTRW) Remedial Action Projects Appropriate federal, state, and local permits should be identified in this paragraph, and site specific permit requirements should also be provided. For projects where a permit is required, usually the State agency will issue an air p
43、ollution control permit (or permit equivalent) that will specify emissions control requirements. The following requirement is an example from a State air pollution control permit equivalent, “The maximum emission rate of total VOC shall not exceed 0.092 lbs/hr“.*Air emissions shall be monitored, controlled, and reported in