    REG NASA-LLIS-5156-2011 Lessons Learned Pad-39A Sandblast Pot Mishap.pdf

    • 资源ID:1019483       资源大小:92.99KB        全文页数:2页
    • 资源格式: PDF        下载积分:10000积分
    快捷下载 游客一键下载
    账号登录下载
    微信登录下载
    二维码
    微信扫一扫登录
    下载资源需要10000积分(如需开发票,请勿充值!)
    邮箱/手机:
    温馨提示:
    如需开发票,请勿充值!快捷下载时,用户名和密码都是您填写的邮箱或者手机号,方便查询和重复下载(系统自动生成)。
    如需开发票,请勿充值!如填写123,账号就是123,密码也是123。
    支付方式: 支付宝扫码支付    微信扫码支付   
    验证码:   换一换

    加入VIP,交流精品资源
     
    账号:
    密码:
    验证码:   换一换
      忘记密码?
        
    友情提示
    2、PDF文件下载后,可能会被浏览器默认打开,此种情况可以点击浏览器菜单,保存网页到桌面,就可以正常下载了。
    3、本站不支持迅雷下载,请使用电脑自带的IE浏览器,或者360浏览器、谷歌浏览器下载即可。
    4、本站资源下载后的文档和图纸-无水印,预览文档经过压缩,下载后原文更清晰。
    5、试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓。

    REG NASA-LLIS-5156-2011 Lessons Learned Pad-39A Sandblast Pot Mishap.pdf

    1、Public Lessons Learned Entry: 5156 Lesson Info: Lesson Number: 5156 Submitting Organization: KSC Submitted by: Dawn Martin Subject: Pad-39A Sandblast Pot Mishap Abstract: A worker disconnected a hose from the vent pipe attached to a sandblast pot, the stored pressure energy in the pot caused the pip

    2、e to spin, and the worker was struck several times by the spinning vent pipe. The injured worker and several others involved in the sandblasting operation were employed under a subcontract to perform corrosion control, including sandblasting and painting. The oversight of equipment configuration and

    3、 operations delegated to subcontractors can lead to unsafe operations. All pressure system maintenance should be performed by approved procedures that ensure configuration control and prime contractors should explicitly identify in their subcontracts the maintenance that subcontractors are authorize

    4、d to perform without obtaining prime-contractor approval. Description of Driving Event: On July 19, 2006, at approximately 0714, Eastern Daylight Time, a sandblasting worker was struck several times by a spinning vent pipe assembly (consisting of 2-inch galvanized-steel pipes and fittings and a 2-in

    5、ch bronze vent valve) attached to a sandblast pot while preparing for sandblast operations at the Kennedy Space Center (KSC) Launch Complex 39A (Pad 39A). Security, Fire/Rescue, and Emergency Medical Services (EMS) personnel arrived at the scene within a few minutes, and the injured worker was airli

    6、fted to a nearby medical center. The injured worker and several others involved in the sandblasting operation were employed under a subcontract to perform corrosion control, including sandblasting and painting. The mishap involved the unsafe configuration of the sandblast pot due to the following de

    7、ficiencies in the initial system setup of the pressure vessel/systems (PV/S): No safety relief valve (SRV) in the system was set at or below the maximum allowable working pressure (MAWP) of the sandblast pot (lowest-rated component in the system), as required by the American Society of Mechanical En

    8、gineers (ASME). The sandblast pot was not equipped with a pressure gage or SRV as required by OSHA 29 CFR. Operating pressure was set higher than the sandblast pot (receiver) MAWP. The manufacturers certification was voided by postmanufacturing welds on the pressure vessel. The SRVs on the compresso

    9、r and dryer did not open at the designated settings of the valves. The compressor SRV was missing the appropriate manufacturers identification plate. Flex hoses and other components of the dryer were in disrepair. Lesson(s) Learned: Fixed Priced Contractors (FPC) construction subcontractors oversigh

    10、t did not discover the unsafe configuration of the sandblast pot. The quality and focus of the oversight of equipment configuration and operations delegated to subcontractors can lead to unsafe operations. Recommendation(s): 1. Ensure the inventory of pressure vessels is known, that the certificatio

    11、n of these vessels is in accordance with your safety requirements, and that your pressure vessel safety requirements are clear, concise, and comprehensive. 2. Ensure that modifications to pressure systems are managed and controlled by configuration management in order to ensure that safety is not co

    12、mpromised regardless of ownership at the Center. All pressure system maintenance should be performed by approved procedures that ensure configuration control, including the use and approval of parts that are not from the original equipment manufacturer (OEM). 3. Ensure that modifications to Commeric

    13、al Off The Shelf (COTS) equipment goes through an approval by the manufacturer and/or an approval by the Centers safety engineering organization. Also, a documented process to should be developed and followed. 4. Ensure that daily safety inspections are performed and that those records are maintaine

    14、d. 5. Ensure that field maintenance is performed by the responsible equipment owner in accordance with manufacturer requirements. 6. All KSC prime contractors who manage PV/S at KSC should explicitly identify in their subcontracts the maintenance that subcontractors are authorized to perform without

    15、 obtaining prime-contractor approval. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Evidence of Recurrence Control Effectiveness: N/A Documents Related to Lesson: KNPR 8715.3 KSC Safety Practices Procedural Requirements NASA STD 8719.17 NASA Requir

    16、ements for Ground-Based Pressure Vessels and Pressurized Systems KSC-PLN-2807 Mishap Contingency Plan Mission Directorate(s): Exploration Systems Additional Key Phrase(s): Facilities Review systems and boards Maintenance Configuration Change Control Role of Civil Service Technical Staff versus Contr

    17、actor Staff Risk Management Contractor Relationships Communications between Different Offices and Contractor Personnel Acquisition / Procurement Strategy and Planning Pressure Vessels Additional Info: Project: Shuttle Program Approval Info: Approval Date: 2011-02-16 Approval Name: mbell Approval Organization: HQ Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-


    注意事项

    本文(REG NASA-LLIS-5156-2011 Lessons Learned Pad-39A Sandblast Pot Mishap.pdf)为本站会员(dealItalian200)主动上传,麦多课文档分享仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。 若此文所含内容侵犯了您的版权或隐私,请立即通知麦多课文档分享(点击联系客服),我们立即给予删除!




    关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1 

    收起
    展开