欢迎来到麦多课文档分享! | 帮助中心 海量文档,免费浏览,给你所需,享你所想!
麦多课文档分享
全部分类
  • 标准规范>
  • 教学课件>
  • 考试资料>
  • 办公文档>
  • 学术论文>
  • 行业资料>
  • 易语言源码>
  • ImageVerifierCode 换一换
    首页 麦多课文档分享 > 资源分类 > PDF文档下载
    分享到微信 分享到微博 分享到QQ空间

    REG NASA-LLIS-4236-2010 Lessons Learned - Facility Building B1201 Roof Repair Mishap.pdf

    • 资源ID:1019446       资源大小:116.61KB        全文页数:2页
    • 资源格式: PDF        下载积分:10000积分
    快捷下载 游客一键下载
    账号登录下载
    微信登录下载
    二维码
    微信扫一扫登录
    下载资源需要10000积分(如需开发票,请勿充值!)
    邮箱/手机:
    温馨提示:
    如需开发票,请勿充值!快捷下载时,用户名和密码都是您填写的邮箱或者手机号,方便查询和重复下载(系统自动生成)。
    如需开发票,请勿充值!如填写123,账号就是123,密码也是123。
    支付方式: 支付宝扫码支付    微信扫码支付   
    验证码:   换一换

    加入VIP,交流精品资源
     
    账号:
    密码:
    验证码:   换一换
      忘记密码?
        
    友情提示
    2、PDF文件下载后,可能会被浏览器默认打开,此种情况可以点击浏览器菜单,保存网页到桌面,就可以正常下载了。
    3、本站不支持迅雷下载,请使用电脑自带的IE浏览器,或者360浏览器、谷歌浏览器下载即可。
    4、本站资源下载后的文档和图纸-无水印,预览文档经过压缩,下载后原文更清晰。
    5、试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓。

    REG NASA-LLIS-4236-2010 Lessons Learned - Facility Building B1201 Roof Repair Mishap.pdf

    1、 Public Lessons Learned Entry: 4236Lesson Info:a71 Lesson Number: 4236 a71 Lesson Date: 2010-10-22 a71 Submitting Organization: SSC a71 Submitted by: Robert Traill Subject: Facility Building B1201 Roof Repair Mishap Abstract: During weekend work conducted February 3 and 4, 2007, contract workers rem

    2、oved the existing B1201 roof material, which uncovered an old drain (drain 1). This drain 1 had been abandoned in place, the drain pipe had been cut, and vertical section removed below the roof deck. During the same activity the roofers broke the PVC bowl of a nearby active drain (drain 2). The work

    3、ers, believing that drain 1 was viable, proceeded to unblock the drain pipe and finished the drain location to the completed roof. As part of the same operation, the workers did not repair the drain 2 damage, instead they covered over this drain. Over one (1) inch of rain fell at the Stennis Space C

    4、enter during the night of February 12th and the morning of the 13th. Rain entered B1201 through drain 1; the rain fell on and damaged several pieces of IT equipment. In a separate location another drain pipe connection to an internal drain also failed, allowing water to flood an adjacent hallway. Th

    5、is incident was classified a Type B Mishap according to NPR 8621.1B - NASA Procedural Requirements for Mishap Reporting, Investigation, and Recordkeeping. The proximate causes leading to the mishap are listed below. 1. The abandoned drain (drain 1) opened at roof level. 2. The opened, abandoned drai

    6、n (drain 1) pipe ended above IT equipment. Description of Driving Event: NASA/SSC Facility Operating Services Contractor (FOSC) contracted with the roofing contractor to repair through replacement Hurricane Katrina damage to B 1201 roof. The prime contractor then subcontracted the work to a sub-tier

    7、 contractor, notifying the FOSC of his action. The sub-tier contractor further subcontracted the work to a third-tier subcontractor; FOSC was not notified of this last action. FOSC was not aware of a third-tier contractor on site as the workers information for access badges was provided as though th

    8、ey were the second-tier contractors labor force. Contractual and notification information that normally flows to sub-tier contractors did not reach the third-tier contractor. The third-tier contractor did not know to notify FOSC of the anomalous condition at the roof site. Lesson(s) Learned: 1. Invo

    9、lve the Facility Manager at design reviews to ensure that knowledge of any prior and undocumented facility modifications is captured. 2. Make a thorough sweep of all Engineering Modification Instructions (EMI) packages and shop work orders for the facility undergoing modification. 3. Require prime c

    10、ontractors to disclose all sub-tier contractors that are required in the performance of the work. 4. All contractors - prime and sub - shall participate in pre-construction meetings. Recommendation(s): 1. Include standard questions on field changes in weekly Facility Operating Services (FOS) constru

    11、ction notes. 2. Test all drains per existing specifications to ensure they are functional. 3. Evaluate drains, close and remove inactive ones. 4. Conduct thorough inspection of all roof drains per specifications, including areas covered by drop ceiling tiles when drain pipes are internal to the buil

    12、ding. Evidence of Recurrence Control Effectiveness: N/A Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Documents Related to Lesson: Investigation of the SSC Building 1201 Roof Failure Type B Mishap. IRIS number 2007-045-00001 Mission Directorate(s):

    13、 N/A Additional Key Phrase(s): a71 Maintenance a71 International partner coordination a71 Contractor relationships a71 Communications between different offices and contractor personnel a71 Acquisition / procurement strategy and planning a71 Facilities a71 Ground processing and manifesting a71 Review systems and boards Additional Info: a71 Project: N/A Approval Info: a71 Approval Date: 2010-11-18 a71 Approval Name: mbell a71 Approval Organization: HQ Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-


    注意事项

    本文(REG NASA-LLIS-4236-2010 Lessons Learned - Facility Building B1201 Roof Repair Mishap.pdf)为本站会员(testyield361)主动上传,麦多课文档分享仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。 若此文所含内容侵犯了您的版权或隐私,请立即通知麦多课文档分享(点击联系客服),我们立即给予删除!




    关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1 

    收起
    展开