欢迎来到麦多课文档分享! | 帮助中心 海量文档,免费浏览,给你所需,享你所想!
麦多课文档分享
全部分类
  • 标准规范>
  • 教学课件>
  • 考试资料>
  • 办公文档>
  • 学术论文>
  • 行业资料>
  • 易语言源码>
  • ImageVerifierCode 换一换
    首页 麦多课文档分享 > 资源分类 > PDF文档下载
    分享到微信 分享到微博 分享到QQ空间

    REG NASA-LLIS-0970-2001 Lessons Learned Planning for Transition of Project Management Responsibilities.pdf

    • 资源ID:1018615       资源大小:14.93KB        全文页数:3页
    • 资源格式: PDF        下载积分:10000积分
    快捷下载 游客一键下载
    账号登录下载
    微信登录下载
    二维码
    微信扫一扫登录
    下载资源需要10000积分(如需开发票,请勿充值!)
    邮箱/手机:
    温馨提示:
    如需开发票,请勿充值!快捷下载时,用户名和密码都是您填写的邮箱或者手机号,方便查询和重复下载(系统自动生成)。
    如需开发票,请勿充值!如填写123,账号就是123,密码也是123。
    支付方式: 支付宝扫码支付    微信扫码支付   
    验证码:   换一换

    加入VIP,交流精品资源
     
    账号:
    密码:
    验证码:   换一换
      忘记密码?
        
    友情提示
    2、PDF文件下载后,可能会被浏览器默认打开,此种情况可以点击浏览器菜单,保存网页到桌面,就可以正常下载了。
    3、本站不支持迅雷下载,请使用电脑自带的IE浏览器,或者360浏览器、谷歌浏览器下载即可。
    4、本站资源下载后的文档和图纸-无水印,预览文档经过压缩,下载后原文更清晰。
    5、试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓。

    REG NASA-LLIS-0970-2001 Lessons Learned Planning for Transition of Project Management Responsibilities.pdf

    1、Lessons Learned Entry: 0970Lesson Info:a71 Lesson Number: 0970a71 Lesson Date: 2001-07-26a71 Submitting Organization: HQa71 Submitted by: Wilson HarkinsSubject: Planning for Transition of Project Management Responsibilities Description of Driving Event: In the 1995-1996 timeframe the Office of Safet

    2、y and Mission Assurance (OSMA) began development of a distance learning capability under the umbrella of the Professional Development Initiative (PDI). This distance learning capability eventually evolved from a Safety and Mission Assurance discipline system into the Site for Online Learning and Res

    3、ources (SOLAR) (http:/solar.msfc.nasa.gov), currently one of NASAs primary distance learning resources. The intent of the initial development effort was to design and implement a prototype system for the Safety and Mission Assurance discipline. OSMA managed the project and the Training and Developme

    4、nt Division at NASA Headquarters (Hereafter referred to as the Sponsor) provided the funding. The only stipulation that the Sponsor made was that whatever capability was developed it needed to be adaptable for use across all of the Agencys functional disciplines. The prototype distance learning syst

    5、em was successful and did evolve into SOLAR which is a multi-discipline Agencywide distance learning system.As part of the decision to release SOLAR, OSMA and the Sponsor agreed that since the training materials were no longer limited to just the Safety and Mission Assurance discipline, that at some

    6、 point in time the Sponsor would assume responsibility from OSMA for day-to-day management of the overall system. OSMA and the other functional discipline areas would retain responsibility for their individual discipline segments of the system including their specific course materials. No milestone

    7、was established for the transition of responsibility and no planning was conducted to prepare for the transition. Both the OSMA Project Team and the Sponsor assumed that there would be adequate opportunity to plan and prepare for the transition of responsibility.Unfortunately, changing needs within

    8、OSMA dictated identification of a transition date with short notice for planing, preparation and implementation. Of course no time is a perfect time for a transition, which was also the case here as several other issues were also consuming both the Provided by IHSNot for ResaleNo reproduction or net

    9、working permitted without license from IHSSOLAR Project Team and the Sponsors time. Since there had been no transition planning on the part of either the SOLAR Project Team or the Sponsor several issues quickly materialized. The principle one being that the OSMA was not going to transfer any human r

    10、esources to continue Project management responsibility and the Sponsor did not have any staff with sufficient time available to assume that responsibility. While OSMA and the Sponsor did eventually complete the management transition it did adversely affect SOLAR by essentially stalling all new syste

    11、m development work while the transition team focused on completing the transition and maintaining day-to-day system operational capability.Lesson(s) Learned: The time to start transition planning for any transfer of functional responsibility is immediately after the decision is made that a transitio

    12、n will occur, regardless of how far in the future that transition may take place. Early planning allows the project participants the opportunity to coordinate a responsibility transfer concurrent with existing and planned work rather than being controlled by external factors and forced to defer proj

    13、ect activities.Recommendation(s): Initiate planning for transfer of responsibilities as soon as the decision to make the transfer occurs. If a project is a proof-of-concept activity like the original PDI distance learning project, the development work should include planning to transition to full op

    14、erating capability.Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): N/AAdditional Key Phrase(s): a71 Administration/Organizationa71 Policy & Planninga71 Training EquipmentProvided by IHSNot for Resale-,-,-Additional Info: Approval Info: a71 Approval Date: 2001-07-30a71 Approval Name: Eric Raynora71 Approval Organization: QSa71 Approval Phone Number: 202-358-4738Provided by IHSNot for Resale-,-,-


    注意事项

    本文(REG NASA-LLIS-0970-2001 Lessons Learned Planning for Transition of Project Management Responsibilities.pdf)为本站会员(twoload295)主动上传,麦多课文档分享仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。 若此文所含内容侵犯了您的版权或隐私,请立即通知麦多课文档分享(点击联系客服),我们立即给予删除!




    关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1 

    收起
    展开