欢迎来到麦多课文档分享! | 帮助中心 海量文档,免费浏览,给你所需,享你所想!
麦多课文档分享
全部分类
  • 标准规范>
  • 教学课件>
  • 考试资料>
  • 办公文档>
  • 学术论文>
  • 行业资料>
  • 易语言源码>
  • ImageVerifierCode 换一换
    首页 麦多课文档分享 > 资源分类 > PDF文档下载
    分享到微信 分享到微博 分享到QQ空间

    REG NASA-LLIS-1569--2005 Lessons Learned Lack of Project-level Reserves.pdf

    • 资源ID:1019192       资源大小:12.90KB        全文页数:2页
    • 资源格式: PDF        下载积分:10000积分
    快捷下载 游客一键下载
    账号登录下载
    微信登录下载
    二维码
    微信扫一扫登录
    下载资源需要10000积分(如需开发票,请勿充值!)
    邮箱/手机:
    温馨提示:
    如需开发票,请勿充值!快捷下载时,用户名和密码都是您填写的邮箱或者手机号,方便查询和重复下载(系统自动生成)。
    如需开发票,请勿充值!如填写123,账号就是123,密码也是123。
    支付方式: 支付宝扫码支付    微信扫码支付   
    验证码:   换一换

    加入VIP,交流精品资源
     
    账号:
    密码:
    验证码:   换一换
      忘记密码?
        
    友情提示
    2、PDF文件下载后,可能会被浏览器默认打开,此种情况可以点击浏览器菜单,保存网页到桌面,就可以正常下载了。
    3、本站不支持迅雷下载,请使用电脑自带的IE浏览器,或者360浏览器、谷歌浏览器下载即可。
    4、本站资源下载后的文档和图纸-无水印,预览文档经过压缩,下载后原文更清晰。
    5、试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓。

    REG NASA-LLIS-1569--2005 Lessons Learned Lack of Project-level Reserves.pdf

    1、Lessons Learned Entry: 1569Lesson Info:a71 Lesson Number: 1569a71 Lesson Date: 2005-06-05a71 Submitting Organization: ARCa71 Authored by: Ronald C. WinterlinSubject: Lack of Project-level Reserves Abstract: The AATT Project was directed, at the Non-Advocate Review (NAR), to not maintain a reserve, w

    2、hich significantly hampered the projects ability to mitigate risk and address unforeseen situations. Most schools-of-thought recognize the importance of any project manager maintaining a reasonable reserve for purposes of risk management and mitigation. Having no other option but to re/de-scope in s

    3、ome fashion obviously has negative effects on the project and its ability to deliver completely and on time. Description of Driving Event: During the AATT Project, the requirement to re-plan or de-scope the project was necessary to support shifts in customer and stakeholder needs. The ability for a

    4、project to effectively and efficiently make significant midcourse adjustments is impacted by the lack of a budget reserve. Lesson(s) Learned: The lesson learned from the AATT Project is to ensure projects are authorized to maintain a funding reserve and this is honored and maintained throughout the

    5、life of the project. Often time project reserves are really not what they appear and are not made available to individual project managers granted necessary authority to make and implement decisions regarding their expenditure. Recommendation(s): Obviously, sufficient recognized reserve amounts must

    6、 be designated for project management use and preserved, as stated above. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): a71 Exploration Systems

    7、a71 Sciencea71 Aeronautics Researcha71 Space OperationsAdditional Key Phrase(s): a71 Air-Traffic Managementa71 Policy & Planninga71 Program and Project Managementa71 Risk Management/AssessmentAdditional Info: Approval Info: a71 Approval Organization: ARCProvided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-


    注意事项

    本文(REG NASA-LLIS-1569--2005 Lessons Learned Lack of Project-level Reserves.pdf)为本站会员(proposalcash356)主动上传,麦多课文档分享仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。 若此文所含内容侵犯了您的版权或隐私,请立即通知麦多课文档分享(点击联系客服),我们立即给予删除!




    关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1 

    收起
    展开