1、Lessons Learned Entry: 1524Lesson Info:a71 Lesson Number: 1524a71 Lesson Date: 2004-07-01a71 Submitting Organization: MSFCa71 Submitted by: Donald DugalSubject: Next Generation Launch Technology (NGLT)/Develop an Integrated Master Schedule in the Formulation Phase Abstract: Due to the creation of NG
2、LT as a merger of two different programs, the Program had not fully achieved one integrated master schedule linking all NGLT projects with standardized schedule formats at the time of Program closing. Programs should clearly identify milestones that all projects need to meet (versus a roll-up of pro
3、ject-level milestones) during formulation. Description of Driving Event: Due to the creation of NGLT as a merger of two different programs, the Program had not fully achieved one integrated master schedule linking all NGLT projects with standardized schedule formats at the time of Program closing. T
4、here was some difficulty identifying all key interrelationships between the projects. Another hindrance was the discrepancies with the Integrated Budget and Performance Document (IBPD) milestone dates and the milestone descriptions, especially during the merger process. Later, NGLT placed the milest
5、ones under full configuration management.Lesson(s) Learned: The level of participation by schedulers in all relevant project and program activities limited the NGLT schedule process.Recommendation(s): Programs should clearly identify milestones that all projects need to meet (versus a roll-up of pro
6、ject-level milestones) during formulation. This would allow the projects to produce schedules with direct Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-links to a program integrated master schedule. The programs should require early compliance with
7、 schedule standardization guidelines, with some accommodations for contractor issues. Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): a71 Exploration Systemsa71 Space Operationsa71 Aeronautics ResearchAdditional Key Phrase(s): a71 Policy & Planninga71 Program and Project ManagementAdditional Info: Approval Info: a71 Approval Date: 2005-04-29a71 Approval Name: Lisa Carra71 Approval Organization: MSFCa71 Approval Phone Number: 256-544-2544Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-