欢迎来到麦多课文档分享! | 帮助中心 海量文档,免费浏览,给你所需,享你所想!
麦多课文档分享
全部分类
  • 标准规范>
  • 教学课件>
  • 考试资料>
  • 办公文档>
  • 学术论文>
  • 行业资料>
  • 易语言源码>
  • ImageVerifierCode 换一换
    首页 麦多课文档分享 > 资源分类 > PDF文档下载
    分享到微信 分享到微博 分享到QQ空间

    REG NASA-LLIS-1497-2003 Lessons Learned - Orbital Space Plane Development and Planning Documentation.pdf

    • 资源ID:1019135       资源大小:14.86KB        全文页数:3页
    • 资源格式: PDF        下载积分:10000积分
    快捷下载 游客一键下载
    账号登录下载
    微信登录下载
    二维码
    微信扫一扫登录
    下载资源需要10000积分(如需开发票,请勿充值!)
    邮箱/手机:
    温馨提示:
    如需开发票,请勿充值!快捷下载时,用户名和密码都是您填写的邮箱或者手机号,方便查询和重复下载(系统自动生成)。
    如需开发票,请勿充值!如填写123,账号就是123,密码也是123。
    支付方式: 支付宝扫码支付    微信扫码支付   
    验证码:   换一换

    加入VIP,交流精品资源
     
    账号:
    密码:
    验证码:   换一换
      忘记密码?
        
    友情提示
    2、PDF文件下载后,可能会被浏览器默认打开,此种情况可以点击浏览器菜单,保存网页到桌面,就可以正常下载了。
    3、本站不支持迅雷下载,请使用电脑自带的IE浏览器,或者360浏览器、谷歌浏览器下载即可。
    4、本站资源下载后的文档和图纸-无水印,预览文档经过压缩,下载后原文更清晰。
    5、试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓。

    REG NASA-LLIS-1497-2003 Lessons Learned - Orbital Space Plane Development and Planning Documentation.pdf

    1、Lessons Learned Entry: 1497Lesson Info:a71 Lesson Number: 1497a71 Lesson Date: 2003-07-01a71 Submitting Organization: MSFCa71 Submitted by: Lisa CarrSubject: Orbital Space Plane/Development and Planning Documentation Abstract: The Orbital Space Plane (OSP) lacked development and planning documents.

    2、These documents may have aided the program in proceeding to the next level. Description of Driving Event: OSP planning documents were not sufficiently mature when the decision was made to embark on an accelerated program.Lesson(s) Learned: OSP planning documents were not sufficiently mature when the

    3、 decision was made to embark on an accelerated program. Parallel development during program execution deadened the sense of urgency to complete them. Absent these documents, unseen organizational friction and implementation inefficiencies resulted. Additionally: a. Program Plan and SEMP The OSP Prog

    4、ram Plan, Systems Engineering Management Plan (SEMP) and related foundational plans (Risk Management, Configuration and Data Management, Records Plans, etc.) were not sufficiently mature when the decision was made to embark on an accelerated program. Parallel development during program execution dea

    5、dened the sense of urgency to complete them b. Schedule Planning and Implementation A lack of standardization of inputs from various centers and organizations complicated the Integrated Master Schedule baseline and updates. Additionally, in response to acceleration of the program, two separate sched

    6、ules of ongoing and planned work were Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-being maintained. c. Flight Test Planning Flight test has a major impact on technical, schedule, and budget planning and should be considered in up-front planning.

    7、Schedules leading to verification by flight testing need to be assessed for credibility. d. Program Shutdown The OSP program ceased abruptly. Some key players were reassigned early, including both managers and administrative personnel thus further complicating the shutdown task. Geographically dista

    8、nt centers relied on web-sites and electronic meeting notices and calendars but, these tools were not updated regularly and then shutdown prior to programs end. Recommendation(s): It is a mistake to proceed with a program without at least a fully developed, documented, and communicated Program Plan

    9、and Systems Engineering Management Plan. Parallel development during program execution can deadened the sense of urgency to complete them. Standardize inputs from various centers and organizations to aid in the smooth execution of the Integrated Master Schedule baseline and updates. Schedules leadin

    10、g to verification by flight testing need to be assessed for credibility. NASA should establish procedures to perform an orderly shutdown of programs which are cancelled /terminated/ transitioned. This process should include the following, at a minimum: procedure to efficiently transition civil servi

    11、ce and support contractors back into the workforce to maintain productivity and morale; procedure/format to document lessons learned by government and contractors (if required); defined communication paths to inform employees of management decisions throughout the transition; and a procedure to real

    12、locate physical resources/equipment into the center infrastructure. Agency/Center management needs to take a proactive approach to support the displaced employees and show appreciation for accomplishments/successes, as appropriate. Close-out should be considered the last stage of a project - not sim

    13、ply the delivery of the products to the customer. Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AProvided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Mission Directorate(s): a71 Exploration Systemsa71 Space Operationsa71

    14、Aeronautics ResearchAdditional Key Phrase(s): a71 Policy & Planninga71 Program and Project ManagementAdditional Info: Approval Info: a71 Approval Date: 2005-04-01a71 Approval Name: Lisa Carra71 Approval Organization: MSFCa71 Approval Phone Number: 256-544-2544Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-


    注意事项

    本文(REG NASA-LLIS-1497-2003 Lessons Learned - Orbital Space Plane Development and Planning Documentation.pdf)为本站会员(ownview251)主动上传,麦多课文档分享仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。 若此文所含内容侵犯了您的版权或隐私,请立即通知麦多课文档分享(点击联系客服),我们立即给予删除!




    关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1 

    收起
    展开